Terminating the Contract on Account of Fundamental Breach, Whether Innocent Party is Entitled to Claim Damages for the entire Contract ?
Contract Law - Termination of Contract - Once it is established that the party was justified in terminating the contract on account of fundamental breach thereof, then the said innocent party is entitled to claim damages for the entire contract, i.e. for the part which is performed and also for the part of the contract which it was prevented from performing.
IN THE SUPREME COURT OF INDIA
CIVIL APPELLATE
JURISDICTION
(A.K. SIKRI) AND (ASHOK BHUSHAN) JJ.
JANUARY 18, 2018
CIVIL APPEAL NO. 10466 OF 2017
MAHARASHTRA STATE ELECTRICITY DISTRIBUTION COMPANY LTD.
.....APPELLANT(S)
VERSUS
M/S. DATAR SWITCHGEAR LIMITED &
ORS. .....RESPONDENT(S)
J
U D G M E N T
A.K.
SIKRI, J.
The
appellant herein had awarded a contract to the respondent. Dispute had arisen
leading to the constitution of an Arbitral Tribunal (having regard to the
Arbitration Agreement contained in the contract between the parties) and those arbitration
proceedings culminated in the Arbitral Award dated June 18, 2004. An
application under Section 34 of the Arbitration and Conciliation Act, 1996
(hereinafter referred to as the ‘Act’) was filed by the appellant, questioning
the correctness of the Award which was dismissed by the learned Single Judge of
the High Court vide orders dated March 18, 2009 and April 30, 2009 thereby
affirming the Arbitral Award. Intra-court appeal thereagainst, which was
preferred by the appellant, has been dismissed by the Division Bench of the
High Court vide judgment dated October 19, 2013. It is the validity of that
judgment which is the subject matter of the instant appeal.
2) With the
aforesaid preliminary comments on the nature of proceedings, we turn to the
events that took place, in a chronological manner, that are relevant for
deciding the lis:
EVENTS : The respondent was awarded a contract for installation
of Low Tension Load Management Systems (LTLMS) at various locations by the
appellant during the year 1993-1994. The respondent participated in another
tender in the year 1996 for installation of approximately 23000 numbers LTLMS.
The appellant awarded a work order dated January 15, 1997 for installation of
11760 numbers of LTLMS to the respondent against the above tender of 1996 and
the balance quantities were awarded to other tenderers. According to the
appellant, against the installation made by the respondent previously in the
year 1993-1994, there were large scale complaints and the issue of defective
equipments having been supplied by the respondent which issue was being raised
in the press repeatedly. In view of the criticism faced by the respondent, the
respondent voluntarily offered to not only supply 11760 LTLMS against the order
placed in January 1997 but also undertook to replace all defective Low Tension
Switched Capacitators (LTSCs) supplied by them against the previous contract of
1993-1994 with new technology LTLMS and charge the old lease rentals against
the replaced LTSC during the pendency of the earlier contract. The appellant accepting
the package offer by the respondents issued Letter of Intent in respect of
12555 numbers panel of 1993-1994 contract objects to be replaced by new panels
along with additional quantity of 23672 numbers fresh panels. The appellant
finally placed a composite work order dated March 27, 1997 with the respondent
to:
(i) Supply 11,760 numbers equipments against the tender of 1996-1997
contract. B-I Locations;
(ii) 12,555 numbers
replacement of equipments against the 1993-1994 contract – B-II locations;
and
(iii) 23,672 numbers equipments which was a package with the
B-II locations – B-III locations.
Clause
5.1 of the letter of Work Order dated March 27, 1997 provided as under:
“The supply and installation of the LM Systems shall
commence within four months from the date of this work order or opening of
Letter of Credit or receipt of complete list of locations of DTCs whichever is
later. The entire supply and installation of LM System covered under schedules
at Annexure – B-I, Annexure – B-II and Annexure – B-III shall be completed
within twenty months thereafter.”
3) During the
execution of the said contract, some issues arose between the parties. As per
the respondents, the appellant primarily committed two kinds of breaches,
namely, the appellant did not supply the list of location where the contract
objects had to be installed and, further, the appellant also did not renew the Letter
of Credit (LC) through which the lease rentals were being paid for the
installed objects. A series of correspondence was exchanged between the parties
on the aforesaid two counts as the appellant maintained that it had not
committed any fault in respect of any of the aforesaid aspects. As against the
total number of 47497 LTLMS to be installed by the respondents, it installed
17294 numbers and thereafter terminated the contract vide letter dated February
19, 1999 alleging breaches on the part of the appellant which according to the
respondent entitled the respondent to terminate the contract. The respondent
undertook to maintain 17,294 contracts objects installed by them on the condition
that lease rental of the same would be paid by the appellant. The respondent
further claimed that they had manufactured 14,206 numbers objects which were
waiting to be installed for which locations were not intimated by the appellant.
4) As per the appellant, under the original tender of 1996,
the respondent was only entitled to supply and maintain 11760 contract objects
and 12555 replacement of 1993/94 contract was as a package, with 23672 supply
of contract objects and, failure to replace the contract objects of 1993/94
completely disentitled the respondent from the right to supply any contract
object under the additional quantities of 23672 contract objects awarded as package
beyond the ratio in which the B-II locations were replaced vis-a-vis the
additional quantity awarded in B-III locations. Thus, the partial termination
by the respondent was illegal and arbitrary because as against 12,555 B-II
locations, the respondent had installed only 2,014 equipments and thus they were
aware of 10,541 B-II locations which were for replacement basis. Hence it was
incorrect on their part to suggest that they had a right to terminate the
contract due to non-supply of list of locations.
5) A meeting was held between the officials of the
appellant and representatives of the respondent and it was duly recorded in the
Minutes of Meeting dated March 11, 1999 that the Chairman of the appellant had
informed the respondent that the maps were readily available in the Kolhapur
zone and requested the respondent to take up the work immediately. However, the
respondent stated that it was not in a position to start the work immediately.
The appellant wrote letter dated April 5, 1999 to the respondent bringing out
its extreme dissatisfaction in the manner in which the work was being carried
out by the respondent and calling upon the respondent to stick to the
implementation of the programme as per the terms and conditions of the Work
Order. The
respondent by letter dated April 21, 1999 terminated the contract in its
entirety and refused to maintain even the objects installed by them.
6) Dispute having arisen; for adjudicating these disputes,
Arbitral Tribunal in terms of Arbitration Agreement was constituted. The Tribunal
commenced its proceedings on February 19, 1999 and on June 18, 2004 passed a
final award directing the appellant to pay Rs.185,97,86,399/- to the respondent
as damages which included:
(i) Rs. 109 crores towards the installed object.
(ii) Rs. 71 crores
towards the objects manufactured by the respondent which were ready for
installation which they claimed could not be installed due to lack of list of
locations; and
(iii) Rs. 6.52 crores towards raw material allegedly purchased
by the respondent for the manufacture of remaining equipments.
7) As aforesaid, before the arbitrators, the respondents
had primarily contended two defaults by the appellant. First, that the
appellant did not supply the list of locations where the contract objects had to
be installed and second, that the appellant did not renew the LC through which
the lease rentals were being paid for the installed objects.
8) The Arbitral Tribunal, however, found no fault with the
appellant as regards non-renewal of the LC observing that the respondent had
terminated the contract in its entirety on April 21, 1999 whereas the LC was
valid upto April 30, 1999. The
finding regarding non-renewal of LC by the Arbitral Tribunal was affirmed by
the learned Single Judge (Justice D.K. Deshmukh)
vide judgment dated August 3, 2005 when the Award was initially set aside. The
said finding was also affirmed by the Ld. Division Bench of the Bombay High
Court vide its judgment dated October 22, 2008. However, partly allowing the
appeal of the respondent, the judgment of the learned Single Judge dated August
3, 2005 was set aside and the matter was remanded back for fresh consideration.
While adopting this course of action, the Division Bench in its judgment dated
October 22, 2008 observed as under:
“44.
The Court if decides an application under Section 34 should either expressly or
impliedly say that the award was being set aside because it was contrary to the
terms of the contract or the Award was in any way violative of the public
policy or the award was contrary to the substantive law in India viz., Sections
55 and 73 of the Indian Contract Act or the award was vitiated by perversity in
evidence in contract or the adjudication of a claim has been made in respect
whereof there was no dispute or difference or the award was vitiated by internal
contradictions. In the present judgment which is under challenge, we have not
found any such findings either expressly or impliedly though in the pleadings
the issues were raised which should be the subject matter of a petition under
Section 34 of the Act of 1996. Therefore, we find that it will be necessary for
this Court to set aside the judgment impugned and remand the case back for
adjudication afresh in accordance with the parameters set out by Section 34 of
the 1996 Act.
45. In view of
the above, the appeal is allowed. Impugned
judgment and order dated 3rd August 2005 passed by the learned Judge of this Court in
Arbitration Petition No. 374 of 2004 is set aside. The case is remanded back
for adjudication afresh in accordance with the parameters set out by Section 34
of the Arbitration and Conciliation Act, 1996.”
9) After the remand, the learned Single Judge (Justice
Roshan Dalvi) by order dated March 18, 2009 rejected the case of the appellant
on the ground that no case under Section 34(2)(iv) of the Act had been made out
by the appellant. The aforesaid order dated March 18, 2009 of the learned
Single Judge was challenged by the appellant before the Division Bench of the Bombay
High Court. The Division Bench, while hearing the appeal, passed the following
order on April 21, 2009:
“1. Learned
counsel for the petitioner has tried to submit before this Court that certain
arguments quoted by the learned Single Judge in the impugned judgment were not
argued by him and they have been put up by the learned Single Judge in his
mouth. Under these circumstances we find it appropriate to direct the petitioner
to approach the Ld. Single Judge seeking correction and/or withdrawal and/or
the modification of the submission which are put up in his mouth. After appropriate
orders are passed by the Ld. Single Judge, appeal be placed for admission.
2. Appeal No.
165 of 2009 be heard along with this Appeal.
3. Since
contentions raised before the Ld. Single Judge are in dispute as stated above
and the Petitioner has been directed to approach the Ld. Single Judge for the purpose
of correction and/or modification, and also in view of the fact that the
impugned order has not attained finality for the purpose of being considered by
us, we find it inappropriate to consider Notice of Motion (being Notice of
Motion No. of 2009) for interim relief at this stage. The said notice of motion
will be considered after the appropriate orders are passed by the Ld. Single Judge
on approach to the Ld. Single Judge by the Petitioner.”
10) The learned Single Judge by order dated April 30, 2009 clarified
her order by saying that although the appellant has argued the matter
challenging the award being beyond the contract between the parties and being
opposed to public policy, the learned Single Judge in her considered opinion
rejected the same under Section 34(2)(iv) of the Act.
11) Appeal of the appellant was thereafter listed before the
Division Bench in which order dated May 2, 2009 was passed staying the Award
upon the condition that the appellant deposits the principal amount and submits
bank guarantee qua
the interest awarded by the
arbitrators. This order was challenged by both the parties by filing their
respective SLP. This Court while hearing these SLPs, modified the order of the
High Court, directing the appellant to deposit Rs.65 crores with the Bombay
High Court and furnish a bank guarantee in the sum of Rs.200 crores. Amount
of Rs.65 crores was allowed to be withdrawn by the appellant upon furnishing
bank guarantee subject to the outcome of the appeal before the High Court.
12) In the appeal before the High Court, the appellant
raised certain additional grounds. Thereafter, the matter was heard finally and
vide impugned judgment, the appeal of the appellant has been dismissed by the
High Court.
ORDER OF THE HIGH COURT
13) Before
adverting to the arguments that are advanced by Mr. Vikas
Singh, learned senior counsel appearing for the appellant and reply thereto of
Mr. Rafique Dada, learned senior counsel who appeared for the respondent, it
would be wise to scan through the impugned judgment of the Division Bench in
order to understand and appreciate the line of reasoning which is the basis of
justifying and upholding the order of the learned Single Judge and dismissing
the objections of the appellant to the award rendered by the Arbitral Tribunal.
In a very elaborate judgment, which runs into more than 150 pages, the High
court has discussed various facets of the case under the following heads:
1. Brief Synopsis and chronology of events.
2. Remand
3.
Submissions and finding on interpretation of the order of Apex Court dated
25/8/2009 passed in SLP filed by MSEB, challenging the order of remand passed
by the Division Bench of this Court headed by Bilal Nazki, J
4. Notice of
Motion No.3227 of 2010
5. Notice of Motion No.461 of 2010.
6. Scope of
interference under Sections 34 and 37 of the said Act; the interpretation of
the term "public policy" and; power of the Court to interfere on that
ground.
7. Points (i)
to (vi) extensively urged by MSEB
8. Submissions and finding on Point No.(i)
Whether the Arbitral Tribunal and the learned Single Judge were justified in
coming to the conclusion that the MSEB had committed breach of contract by not
supplying DTC Lists?
9. Submissions and finding on Point No.(ii) Whether the contract
was one complete contract and the same could not be split up as argued by the
Claimants?
10. Submissions and finding on Point No.(iii) Whether Claimants/DSL
waived their right to receive complete lists of locations; and on Point No (iv)
Whether the Award is contrary to the public policy as mentioned under Section
34 of the Arbitration and Conciliation Act, 1996?
11. Submissions and finding
on Point No. (iv) Whether the Award is contrary to the Public Policy as mentioned
under Section 34 of the Arbitration and Conciliation Act, 1996? (v) Whether the
damages were properly awarded? and (vi) Whether the aspect of mitigation was
properly considered?
12. Chamber Summonses filed by MSEB 13. Conclusion.
14) After narrating the scope of the work and the gist of
the dispute which led to initiation of arbitration proceedings, the High Court
noted that respondent filed its claims under various heads aggregating to
Rs.1053,06,78,342/- and the counter claims of the appellant were to the tune of
Rs.1273,70,26,669/- crores approximately. Appellant had examined as many as 26
witnesses in support of its case whereas the respondent had examined its Managing
Director who was in charge of the project. After conclusion of the evidence and
hearing the arguments, the Arbitral Tribunal partly allowed the claims of the
respondent, holding that respondent was entitled to a sum of Rs. 1,79,15,87,009/-
(Rs. 185,97,86,399 – 6,81,99,390) along with interest @ 10% per annum payable
from the date of the Award till realisation. Cost of rupees one crore was also
awarded. Counter claims of the appellant were dismissed. After taking note of
the aforesaid facts in brief, the High Court dealt with the contention of the
appellant herein that the matter needed to be remanded back to the learned
Single Judge on the ground that the submission of the appellant that the Award
was against the public policy had not been considered by the learned Single
Judge. After comprehensive discussion, this argument has been rejected authoritatively.
In the process, the High Court also dealt with the submissions predicated on
Order dated August 25, 2009 passed by this Court in special leave petition
which was filed by the appellant whereby order of remand passed by Division
Bench of the High Court, in the earlier round was challenged. Notice of Motion
Nos. 3227 of 2010 and 461 of 2010 also came to be included in the discussion
while dealing with the aforesaid issue. Thereafter,
the High Court has discussed the scope of interference under Sections 34 and 37
of the Act, with particular reference to the ground of challenge on the basis
that the award is against “Public Policy of India”. After referring to the law
on this pivotal aspect, the High Court noted the points of arguments advanced
by the appellant affirming part of challenge to the Award. Six points which
were advanced by the appellant in this behalf are as under: (i) Whether the Arbitral Tribunal and the learned Single
Judge were justified in coming to the conclusion that the MSEB had committed
breach of contract by not supplying DTC Lists? (ii) Whether the contract was
one complete contract and the same could not be split up as argued by the
Claimants? (iii) Whether Claimants/DSL waived their right to receive complete lists
of locations? (iv) Whether the Award is contrary to the public policy as mentioned
under Section 34 of the Arbitration and Conciliation Act, 1996? (v) Whether the
damages were properly awarded? (vi)Whether the aspect of mitigation was
properly considered? 15) Thereafter,
discussion ensued on each of the aforesaid issue, one-by-one. On the first
point, the High Court has concluded that the Arbitral Tribunal was justified in
coming to conclusion that the appellant had committed breach of the contract by
not supplying DTC list. While so concluding, the High Court went into the
events which took place in this behalf, gist of the evidence as well as the manner
in which the issue was upraised by the Arbitral Tribunal. The High Court has
held that the finding which was given by the Arbitral Tribunal, after taking into
consideration the rival contentions raised in the claim and in the written
statement on this aspect is a finding of fact which was given after examining
the material on record. The High Court further noted that this finding was
upheld by the learned Single Judge also and the manner in which the learned
Single Judge dealt with the issue has been taken note of. This being a finding of
fact, as per the High Court it was not possible for it to substitute its own
view to the views taken by the Arbitral Tribunal or the learned Single Judge
and arrive at different conclusion, even if two views were possible.
Notwithstanding the same, the Division Bench again examined this very issue on
merits after going through the various clauses in the contract entered into
between the parties. Taking particular note of clauses 5.2 and 5.3, the Division
Bench has affirmed the findings of the Arbitral Tribunal in the following
manner:
“46. Clause 5.2 is also relevant
since it stipulates about the manner in which installation/replacement work was
to be carried out by DSL. The work was to be completed in three Zones, viz.,
Kolhapur Zone, Nasik Zone and Aurangabad Zone. In clause 5.2 sequence of Zones
was mentioned in which the work was to be carried out and it was as under:-
(a)
Kolhapur Zone
(b) Nasik Zone. Work to be commenced on completion of work in
Kolhapur Zone.
(c)
Aurangabad Zone. Work to commence on completion of work in Nasik Zone.
The
sequence therefore was that, first in Kolhapur Zone B-I, B-II, B-III objects
were to be installed and, thereafter, in Nasik again B-I, B-II, B-III objects
were to be installed and finally in Aurangabad, B-I, B-II and B-III objects
were to be installed. The said schedule of completion of work, however, was
changed from time to time and, finally, again, in December, 1998 MSEB informed
DSL to follow the schedule as per clause 5.2.
47.
Clause 5.3 lays down that supply, erection at site and commissioning of the
contract objects was to be done within a stipulated time. It also clarified
that time is the essence of the contract and if there was delay in performance
due to any reason MSEB would be entitled to claim liquidated damages. The chronology
of events indicates that on 14/7/1997, MSEB by its letter informed DSL that
Lists of DTC locations were ready with the Circle Offices and DSL should
collect the same. The case of DSL in brief is that though it was represented by
MSEB that Lists were ready and available on 14/7/1997, Lists were not supplied
and, as a result, installations could not be done and as many as 120 letters
had to be written by DSL to MSEB, requesting them to supply the Lists.
Secondly, sequence of completion of work also was changed from time to time and
suddenly on 21/12/1998 Circle Engineer informed DSL that sequence as per clause
5.2 of the work order had to be adhered to and, DSL was therefore constrained
to send a letter of termination dated 19/02/1999 and even thereafter in a
meeting which was held on 11/3/1999 between the Chairman of the MSEB, DSL and
other two parties who were awarded the contract, as mentioned in clause 17 of
the minutes of the meeting, the Chairman informed DSL that the Lists were
readily available in Kolhapur Zone and asked Mr. Datar to take up the work
under B-II and B-III schedule immediately and the Chairman directed that CEs
present in the meeting that it was the Board's responsibility to give the list
with maps to the agencies and expeditious steps should be taken in that regard.
It was, therefore, contended that as late as 11/3/1999, the Chairman himself
had conceded that the Lists were not made available to DSL. In this context,
certain letters assume importance regarding change of sequence of work.
The
work order dated 27/3/1997 shows that the work initially had to be done in
Kolhapur Zone, then in Nasik Zone and finally in Aurangabad Zone.
Thereafter,
Chief Engineer, MSEB by his letter dated 4/11/1997 changed the sequence and
directed that the work should be completed initially in Nasik Zone in respect
of B-I, B-II, B-III Lists, then in Kolhapur Zone and finally in Aurangabad
Zone. This sequence was again modified by the Chief Engineer's letter dated
25/5/1998 and modification was made in the sequence of schedule and sequence of
zone continued and work could be completed at any stage in any Zone. Again,
third modification was made by Chief Engineer's letter dated 17/6/1998 and
there was modification in respect of Zones and work could be carried out in any
Zone in any sequence.
Then
there was fourth modification by Chief Engineer's letter dated 21/12/1998 and
direction was given to strictly adhere to the original work order sequence.
According to DSL, because the Lists were not supplied though the contract
objects/gadgets were ready for installation and though they were taken to the
sites at the respective Zones, they could not be installed and were lying
stranded causing monetary loss on account of transportation, manual labour etc.
and non-installation of contract objects resulted in DSL not getting benefit of
lease rentals.”
16) Interestingly,
before the Division Bench, the appellant had raised certain additional points on
this aspect, which were not argued before the Tribunal or even before the
learned Single Judge, viz., the non-supply of DTC locations did not amount to breach
of fundamental term of the contract which led to termination of contract by the
respondent. We would like to reproduce, at this stage, this part of discussion
as well:
“48. It must be noted here
that before the learned Single Judge and before this Court, some of the points which
were never urged before the Tribunal had been sought to be urged. In the
written submissions which have been tendered before us and what was urged before
us was that the Arbitral Tribunal had committed serious error by holding that
non- supply of DTC locations amounts to breach of fundamental term of contract
which led to termination of contract by Respondents/Claimants. It has been
contended before us that since each contract object was a separate lease contract,
the Arbitrator's Award has to be considered in three parts (i) qua uninstalled
objects, (ii) qua installed objects and (iii) damages in respect of the objects
not even manufactured and it has to be noted here that Tribunal has framed one
of the points as under:- (A) Whether the
Claimants were ready and willing to perform their part of the contract and if
so, whether Respondents prevented the Claimants from doing so? While answering
this point, the point was discussed in two parts. Firstly, whether the
Claimants were ready and willing to perform their part of the contract and, secondly,
whether Respondents have prevented the Claimants from doing so. In this
context, after having held that Claimants were ready and willing to perform their
part of the contract, while considering the second point, the Tribunal had
taken into consideration the question of supply of DTC Lists and whether it was
a fundamental term of the contract. After having held that MSEB had prevented
DSL from performing their part of the contract even though they were ready and
willing to do so, the question of damages has been thereafter separately
considered and on that point Tribunal has adopted a particular method of
calculation of damages.
In
our view, it is not permissible for MSEB to now change their submissions in
this manner. However, even if the submissions, as advanced before us by MSEB,
are taken into consideration, they are devoid of merits.”
17) Thereafter, the High Court took note of another argument
of the appellant herein, namely, the contract was terminated by the respondent
on account of non-renewal of Letter of Credit in view of respondent’s letter
dated February 19, 1999. However, the High Court did not accept the said
argument as valid and rejected the same. Thereafter, the High Court has
recorded its specific findings on Point No. 1 and we reproduce relevant portion
thereof as under:
“In our view from
the material on record, it is abundantly clear that supply of DTC Lists was a
fundamental term of the Work Order and MSEB had miserably failed in complying
with the said fundamental term and there was a breach on the part of the MSEB
in supplying the DTC locations which eventually prevented DSL from installation
of contract objects. It has to be noted here that after the work order was issued
by MSEB, DSL had to make necessary arrangements for the purpose of carrying out
the process of installation of the contract objects. This included procurement
of raw material from a foreign country, starting the process of manufacturing gadgets,
making arrangements for transportation of these contract objects to the places
where the said gadgets were to be installed, employment of trained, skilled and
other staff, making available vehicles for transporting these contract objects
to the DTC location where they were to be installed and, finally, coordinating with
the Officers of MSEB so that after the contract objects were installed, a
Certificate of installation could be given by the Officers of MSEB so that from
that point onwards, lease rentals could become payable to DSL. It has to be
borne in mind that the nature of the Work Order was such that it was in the
interest of DSL to ensure that the contract objects are installed and certificates
to that effect are obtained from the Officers of MSEB. It does not sound to
reason that after having invested huge amount of almost Rs 163 crores, as observed
by the Tribunal in the Award, DSL would not install the objects because it was
in their interest to get the objects installed so that returns on their huge investment
would start thereafter. It is inconceivable therefore that though DTC Lists
were available, DSL would not install the contract objects. Various facts and figures
were given by MSEB to show that DTC locations were known to DSL and yet they
had failed in installing the contract objects is without any substance. It
cannot be forgotten that, initially, the sequence of installation was Kolhapur,
Nasik and Aurangabad. This sequence was later on changed to Nasik, Kolhapur and
Aurangabad. This was again changed and permission was given to DSL to install
the objects at any time at any place and, lastly, again, this was changed and
direction was given to DSL to adhere to the sequence as per the Work Order.
This being the position, even assuming that B-II Lists were available, DSL
could not have installed these contract objects because they were asked to follow
the schedule again by letter dated 21/12/1998 and, therefore, even if the lists
were available, it was not possible for DSL to simultaneously install all those
objects since they were told to adhere to the sequence in the Work Order if the
lists of locations under B-I were not given, even assuming that they had B-II
lists of locations they could not have and were not actually allowed to install
at the said B-II locations. It has come on record that more than 10,000 objects
were manufactured and ready for installation. There is no earthly reason why
DSL would fail to install the objects which were inspected and ready for
installation. The only obvious reason would be that they were unable to do so
on account of various orders which were passed by MSEB from time to time
preventing them from performing their obligation. MSEB has not examined any of
its Superintending Engineers who were in charge of supplying the Lists. The
cumulative effect of all the material which has been brought on record is that
it clearly demonstrates the failure on the part of MSEB in supplying the Lists
of DTC locations which was a fundamental term of the contract.”
18) Coming to point no. 2, the High Court noted that this
point was not urged before the Tribunal or before the learned Single Judge,
namely, the contract was not one complete contract. For this reason, held the
High Court, it was not permissible for the appellant to urge the same for the
first time before it.
19) Point nos. 3 and 4 were taken up together for discussion. Insofar
as point no. 3 is concerned, the Court noted that relevant provisions in the
light of which this point was to be examined, were Sections 39, 53, 55 and 63
of the Contract Act. The High Court found that when Chief Engineer of the
appellant had written a letter dated December 21, 1998 informing the respondent
that work had to be carried as per the original schedule given in the Work
Order, viz., Kolhapur, Nasik and Aurangabad and a further direction was given
not to install objects at B-III locations, only at that stage the appellant had
refused to perform their part of promise. Only, thereafter, notice was given by
respondent on February 19, 1999 and finally the contract was terminated on
April 21, 1999. Therefore, there was no waiver of right of acquiescence on the
part of the respondent and, thus, argument of the appellant could not be
accepted that the respondent had waived their right to terminate the contract.
The High Court also held that the question of waiver or acquiescence is a
question of fact and since there was a finding of fact by the Arbitral Tribunal
(which was upheld by the Single Judge as well) that there was no waiver or
acquiescence on the part of the respondent, such an argument was not even
available to the appellant in appeal under Section 37 of the Act. On this
basis, the Division Bench rejected the contention of the appellant that the
respondent waived its right to receive complete list of locations. In the
process, the High Court has also rejected the contention of the appellant that
as a consequence of waiver of right to receive list of DTC locations, the only
option which was available to the respondent was to have given notice to the
appellant that it was accepting the performance of the promise other than at
the time agreed upon or that the respondent was entitled to any compensation.
20) With the aforesaid findings on Point no. 3, the High
Court rejected the contention of the appellant that the award of damages was
against the public policy.
21) Thereafter, the High Court discussed the question of quantum
of damages as raised in Point No. 5. It went through the exercise done by the
Arbitral Tribunal in this behalf, i.e., the manner in which the damages are
calculated by the Tribunal. It found that the Tribunal had appreciated to
determine the damages payable to the respondent in respect of lease rent for duration
of seven years for 17294 contract objects which were installed and a figure of
Rs. 108,02,53,173/- in this behalf was arrived at. In respect of 14206 stranded
objects, the Tribunal held that the damages which were payable on account of
aforesaid stranded objects were to the tune of Rs. 14,28,55,536/- for a period
of one year at the rate of Rs. 10,056/- per year for each contract object and
for a duration of five years Rs. 71,42,77,680/-. As
regards those objects which were not manufactured, the Arbitral Tribunal took
into consideration the value of unused imported raw material. On that basis it
came to the conclusion that damages in respect of imported raw material left
unused for 16487 contract objects were Rs. 6,52,55,546/-. In this manner, it arrived
at a total figure of Rs. 185,97,86,399/- and deducted a sum of Rs.
6,81,99,390/- which was paid by the appellant to the respondent pursuant to
interim orders passed by the Tribunal.
22) After taking note of the manner in which the Tribunal awarded
the damages, the High Court noted the challenge of the appellant’s counsel to
the award of damages, which were as under:
(i) Since there was
no breach committed by the appellant and that the respondent had no right to
terminate the contract, no damages were payable.
(ii) Since the cost
of contract object was on an average of Rs. 9,000/- per object, the respondent,
at the best, was entitled to nominal profit of 10-15% on the said cost.
Therefore, the Arbitral Tribunal had granted excessive damages.
(iii) The damages
were wrongly awarded for objects not even manufactured and such an award was in
violation of public policy as mentioned in Section 34 of the Act.
(iv) According to
the understanding of the appellant, the contract was coming to an end on March
19, 1999 and the contract objects, therefore, should have been manufactured by
it. Thus, failure to manufacture the same did not entitle them to claim any
damages qua the objects not manufactured.
(v) Since the
contract was novated, the respondent was obliged to manufacture the objects as
and when the lists were supplied to it and, therefore, the question of payment
of any compensation qua
the objects not manufactured did
not arise.
(vi) There was no
default qua the installed or qua uninstalled
objects and on this ground also the Tribunal was not justified in granting any compensation
whatsoever.
(vii) In respect of
the installed objects, the only breach was non-renewal of the Letter of Credit.
Likewise, in respect of un-installed objects, the only breach was non-submission
of lists of locations. Insofar as non-renewal of Letter of Credit is concerned
Arbitral Tribunal had decided this issue in favour of the appellant and,
therefore, no damages were awardable. In respect of uninstalled objects, the respondent
had 16473 lists of location and they were obliged to maintain 2500 buffer
stock. However, the respondent had manufactured only 14206 objects, therefore,
there was no question of payment of any damages qua uninstalled
objects.
23) Since this issue was connected with Point No. 6, i.e., mitigation
of damages, the High Court dealt with the argument of mitigation as well. Here,
contention of the appellant was that according to the respondents the breach,
if at all, took place only on December 21, 1998 when permission for
simultaneous installation in B-III was withdrawn and no steps whatsoever to remedy
the breach thereafter were taken by the respondents. This
showed that the respondents had not tried to mitigate their loss and were not
entitled to get damages. Here the argument of the respondent was also noted and
after considering the respective arguments, the High court has not found any substance
in the submissions of the appellant. It has given following reasons for
adopting this course of action:
“73.
We agree with the submissions made by the learned Senior Counsel appearing on
behalf of DSL for the following reasons: First of all, it has to be noted that
Arbitral Tribunal in its Award has recorded a finding of fact that MSEB had
committed breach of the contract by not supplying the lists of DTC locations
and this breach was a fundamental breach of the agreement.
Secondly,
it is held that MSEB had prevented DSL from performing its part of the contract
and, therefore, they were entitled to get damages. The Arbitral Tribunal,
thereafter, relying on the Judgment of the Supreme Court in Union of India v/s.
Sugauli Sugar (Pvt.) Ltd. [(1976) 3 SCC 32)] has observed that innocent party
who has proved the breach of contract to supply what he had contracted to get, such
a party should be placed in as good a situation as if the contract had been
performed and, therefore, damages which the Claimants/DSL were entitled to have
to be determined on the said principle. The Tribunal has then held that lease
rent is one of the measures for ascertaining damages and, in that context,
after relying on the Work Order, came to the conclusion that entitlement of the
Claimants was to secure lease rent accrued from the date of installation of the
contract objects. In this context, therefore, for the sake of convenience the
question of quantum of damages was considered with reference to (a)
installation of contract objects, (b) stranded objects and (c) objects not
manufactured.
The
submission of the learned Senior Counsel appearing on behalf of MSEB that the
Arbitral Tribunal had split up the contract into three parts, though the
contract was one single contract, is without any substance. It has to be noted
that the Arbitral Tribunal first came to the conclusion that there was a breach
on the part of MSEB in supplying the lists of DTC locations. Having held, that
there was a breach and that the Claimants/DSL were entitled to claim
compensation, while ascertaining the amount of compensation, for the sake of convenience,
it has considered the aspect of granting damages in the above manner. The
entire thrust of the argument of MSEB, therefore, is misconceived. MSEB has
tried to give a twist to their tale by contending that 17,294 contract objects
being installed, there was no question of awarding damages for the installed
objects and, secondly, since termination of Letter of Credit was held not to be
illegal, it was not open for the Arbitral Tribunal to have awarded damages for
the uninstalled objects and the objects which were not manufactured. This submission
is totally misconceived, firstly because it has been consistently held that the
Arbitral Tribunal alone is competent to decide the manner of calculation of
damages which are to be awarded as also the method which is to be adopted by
the Tribunal. In the present case, the Arbitral Tribunal has held that lease
rent is one of the measures for ascertaining damages. The Apex Court in McDermott vs. Burn Standard [(2006) 11 SCC 181] has observed as under:-
“106. We do
not intend to delve deep into the matter as it is an accepted position that
different formulae can be applied in different circumstances and the question
as to whether damages should be computed by taking recourse to one or the other
formula, having regard to the facts and circumstances of a particular case,
would eminently fall within the domain of the arbitrator.
110. As
computation depends on circumstances and methods to compute damages, how the quantum
thereof should be determined is a matter which would fall for the decision of the
arbitrator. We, however, see no reason to interfere with that part of the award
in view of the fact that the aforementioned formula evolved over the years, is
accepted internationally and, therefore, cannot be said to be wholly contrary
to the provisions of the Indian law."
24) Citing
few more judgments and after extensively quoting therefrom [ (a) Dwarka Das v. State of M.P. and Another (b) ONGC v. Comex (c) Prakash Kharade v. Dr. Vijay Kumar Khandre and Others (d) Grandhi v. Vissamastti (e) Mirza Javed Murtaza v. U.P. Financial Corporation Kanpur and another], the High
Court proceeded further with the discussion as follows:
“The
Arbitral Tribunal, therefore, after having adopted lease rent as one of the
methods of ascertaining damages has thereafter considered what damages should
be awarded by way of lease rentals on installed objects, stranded objects and
the objects not manufactured. In our view, it is not possible to find fault with
the finding of the Arbitral Tribunal on the measure and method for ascertaining
and calculating the damages which have been adopted by it to arrive at the final
figure of compensation to be payable to the Claimants/DSL.
It
is also quite well settled position in law that once it is established that the
party was justified in terminating the contract on account of fundamental
breach of contract then, in that event, such an innocent party is entitled to
claim damages for the entire contract, i.e., for the part which is performed
and also for remaining part of the contract which it was prevented to perform.
This principle is quite well settled in number of cases. The Tribunal,
therefore, was perfectly justified in calculating the damages in the aforesaid
manner. In this view of the matter we do not propose to deal with the judgments
on which reliance is sought to be placed by MSEB.
So
far as the question of mitigation is concerned, the Tribunal has specifically
held that the contract objects were unique objects which had to be manufactured
according to the specifications laid down by the MSEB and, therefore, these
contract objects could not be disposed of in the open market. Even if the said contract
objects were dismantled, value would become nil. The Tribunal also observed
that Datar deposed with reference to Exhibit-C-16 that efforts were made to
sell the contract objects stranded in the factory to other Electricity Boards
but those efforts did not succeed. The question of mitigation, therefore, was
considered by the Tribunal and the submissions of MSEB were not accepted. In
our view, reasoning given by the Tribunal cannot be faulted.”
25) According to the High Court, the Arbitral Tribunal had awarded
damages in a most conservative manner and, thus, committed no illegalities in
awarding these damages. At the end, the High Court dealt with the Chamber
Summons which were filed by the appellant and on detailed discussion thereupon,
dismissed all these Summons.
26) As a consequence, the appeal of the appellant stood dismissed.
ARGUMENTS OF THE APPELLANT :
27) Mr. Vikas Singh referred to the tender of 1993-94,
pursuant to which the respondent had installed 12,555 numbers of LTSC, and
submitted that the respondent was maintaining the same but large scale
complaints about the inefficiency of LTSC was received with the appellant.
Having regard to this criticism faced by the respondent, it volunteered to
replace the installations made in the earlier contract and charge the old
rental in respect of the same. In the meantime, pursuant to tender of the year 1996
for installation, the respondent was awarded work for installation of 11,760
contract objects. Going by the said assurance, the appellant awarded a work
order dated March 27, 1997 for replacement of 12,555 panels of earlier contract
objects plus installation of 23,672 LTMS panels and the work order finally became
as under: (i) Supply 11,760 numbers equipments against the tender of 1996-1997
contract. B-I Locations; (ii) 12,555 numbers
replacement of equipments against the 1993-94 contract – B-II locations;
and (iii) 23,672 numbers equipments which was given as a package with
the B-II Locations – B-III
locations.
28) Mr. Vikas Singh referred to Clause 5.1 of the contract
as per which entire supply and installation of L.M. Systems covered by schedules
at Annexures – B-I, B-II and B-III was to be completed within twenty months. He
thereafter read out the correspondence that was exchanged between the parties
and on that basis, he sought to argue that as per the appellant, the list of
locations was ready on July 14, 1997 but it is the respondent who was facing difficulties
in installation of the contract objects and violating the terms of the contract
with impunity. The respondent had even withdrawn money in excess of its
entitlement. Vide letter dated December 21, 1998, the appellant had written to
the respondent to do installation of B-I and B-II first before B-III locations,
as by that date, the respondent had already installed 17,294 objects out of
which B-II was only 2014. However, the respondents in their reply dated March
21, 1998 asserted their right to install the objects at B-III locations
simultaneously. He further pointed out that in their letter dated February 18,
1999, the respondent admitted having received Rs.4.34 crores in excess of their
entitlement, however, on the very next date, i.e. on February 19, 1999, it
sought to terminate the contract qua the uninstalled
objects numbering 30,695 but volunteered to maintain the installed objects
provided that the rent for the same was forthcoming. It was argued that since
the payment of rent was by means of an irrevocable LC, and since the LC was
valid on February 19, 1999, the offer of maintaining 17,294 objects was clearly
accepted by the appellant as the appellant did not cancel the LC in spite of
termination of the contract qua
uninstalled objects on February 19,
1999. In other words, the LC continued to remain alive even after termination
of the contract on February 19, 1999 in order to make payment of future rentals
qua the uninstalled objects. In spite thereof, the
respondent, vide its communication dated April 21, 1999, terminated the
contract. It was submitted in the aforesaid backdrop that the action of the respondents
was clearly illegal. It was further argued that the findings of the Arbitral
Tribunal that the appellant had committed the fundamental breach of the
contract in not providing the complete list of the contract objects to the
respondents is clearly erroneous which is patently illegal and contrary to the
terms of the contract. It was submitted that the entire premise of the Arbitral
Tribunal to record this finding was on the basis of the letter of the appellant
dated December 21, 1998 which had only debarred the respondent from installing
B-III locations as the respondent was indulging in the malpractice of charging
bills higher than what they were entitled to which is proved by the credit note
given by the respondents themselves on February 18, 1999. The said letter did
not debar the respondent from installing the B-II locations which were 10,541
remaining to be installed on February 19, 1999. The Arbitral Tribunal recorded
a perverse finding which resulted in patent illegality in the award that by
letter dated December 21, 1998 the appellant had debarred the respondent from
installing the B-II locations when clearly neither the same was mentioned in
the said letter nor was the same understood contemporaneously by the respondent
in their response dated December 23, 1999 wherein they merely protested from
being denied the opportunity to install the B-III objects. The Arbitral
Tribunal accordingly committed a grave mistake in holding that the appellant
had committed a fundamental breach when clearly on the date of termination the respondent
had with them 10541 B-II locations and admittedly 1633 B-I locations in
Kolhapur Zone and they were under an obligation under the contract to maintain
2500 buffer objects and hence the respondent had only 14026 contract objects at
that time whereas they were required to maintain at least 14,674 contract
objects on the said date.
29) Next submission of Mr. Vikas Singh, learned senior
counsel, was that the Arbitral Tribunal gave a specific finding that the LC was
valid till April 30, 1999 and there was no default on the part of the appellant
in this behalf, which finding was also confirmed by the learned Single Judge as
well as by the Division Bench which had heard the appeal in the first round.
Therefore, there was no occasion whatsoever for the Arbitral Tribunal to award
damages qua the installed objects as there was no default alleged
and there was no default held to have been committed by the appellant qua the
same.
30) Much emphasis was laid by the learned senior counsel for
the appellant on the order dated August 3, 2005 passed by the learned Single
Judge in the appellant’s petition under Section 34 of the Act (in the first
round), whereby the learned Single Judge had decided the case in favour of the
appellant holding that there could not be any direction for payment of damages
in respect of the installed objects as no default was found by the Arbitral Tribunal
and, therefore, the Tribunal committed a grave mistake in awarding compensation
in respect thereof. In order dated August 3, 2005, the learned Single Judge had
also held that the Arbitral Tribunal had committed illegality by awarding compensation
in respect of the objects manufactured but not installed while permitting the
respondents to retain the same. Likewise,
the award was faulted with to the extent that the Arbitral Tribunal awarded the
amount for the raw material available with the respondent, without directing
the respondent to handover the said raw material to the appellant. Though, this
order dated August 3, 2005 was set aside by the Division Bench in appeal which
was preferred by the respondent, submission of the learned senior counsel was
that it was erroneously set aside on the only ground that the Single Judge
while allowing Section 34 petition had not specifically mentioned the
particular section under which the petition had been allowed when clearly the
order of the learned Single Judge had been passed on the ground that the award
is against the public policy of India and hence it was clearly referable to
Section 34(2)(b)(ii) of the Act. Hence, there was no occasion or necessity to
remand the matter back to the Single Judge of the High Court. Since the
direction by the Division Bench were to the Single Judge was to decide the
matter in a time bound manner, even before the appeal against the order of the
Division Bench could be heard by the Supreme Court, the learned Single Judge of
the Bombay High Court rejected Section 34 petition on a completely erroneous
premise as if that the appellant had argued the case under Section 34(2)(iv)
when admittedly no arguments had been raised under the said Section and the
entire arguments as well as the written submission were only with regard to the
award being contrary to the public policy which is under Section 34(2)(b)(ii).
In this manner, submitted the learned senior counsel, the learned Single Judge
went beyond the mandate of the Division Bench while dismissing the petition of the
appellant in its entirety under Section 34 of the Act and the Division Bench
has also erred in giving its imprimatur to such an order of the Single Judge.
31) Continuing his submissions with great emphasis, Mr.
Vikas Singh further argued that an important issue which need consideration is
as to whether the contract was one complete contract and whether the same could
or could not be split up as argued by the respondents. He referred to the
provisions of the contract, the relevant correspondence and the submission of
the respondents witnesses to refute the respondents contention that the
contract was one bargain and there was no right to split up the same. He also
referred to the certain judgments2
to contend that the contract in
question can be held to be clearly severable and it is the duty of the Courts
to severe the enforceable part vis-Ã -vis the unenforceable part.
2 Firm Bhagwandas Shobhalal Jain, a Registered firm and Anr. v. State of Madhya Pradesh, AIR 1966 MP 95; Shin Satellite Public Co. Ltd. v. Jain Studios Ltd., (2006) 2 SCC 628; Beed District Central Coop. Bank Ltd. v. State of Maharashtra & Ors., (2006) 8 SCC 514, Daruka & Co. v. Union of India & Ors., (1973) 2 SCC 617 and Food Corporation of India v. Yousuff and Co., Kerala High Court (DB) (17.11.1980) A.S. No. 31 of 1976 at Page 2296 (starting from 2280-2297 of volume X)
32) Touching upon the facet of the uninstalled object, it
was submitted that in terms of the work order, the supply and installation was
to commence from the date of the work order or opening of LC or receipt of
complete list of locations of DTCs, whichever is later. On July 14, 1997, the
appellant wrote to the respondents that the list of locations was available
with the circle office. The respondents assumed July 14, 1997 as the date of making
available the complete list of locations without actually receiving the said
list from the circle office. The clause very clearly provided the four month
period to commence from the date of receipt of list of complete locations and
admittedly the respondent did not receive the list of locations on July 14,
1997 nor any time thereafter till they started installation on November 18, 1997,
considering the four month period to start from July 19, 1997 i.e. the date of
receipt of the communication dated July 14, 1997. Clearly, the respondent had
enough time after July 14, 1997 to insist upon the complete list of locations
before any installation was started by them on November 18, 1997. Therefore,
argued the learned senior counsel, it is the respondent which committed breach
of contract in not completing the work.
33) Mr. Vikas Singh once again emphasised the submission which
was made before the learned arbitrator as well as the High Court, that there
was a waiver by the respondent in respect of list of DTC location and the
consequences of such a waiver had to flow as per Section 55 read with Section
63 of the Contract Act. It was submitted that this Court has held in the case
of Waman
Shriniwas Kini v. Ratilal Bhagwandas &
Co., 1959 Supp. (2) SCR 217 at para 13 “waiver
is the amendment of a right which normally everybody had a liberty to waive. A
waiver is nothing unless it amounts to a release it signifies nothing more than
an intention to insist upon the right”. Accordingly, once the waiver takes
place, the clause with regard to providing the complete list does not remain a fundamental
term of the contract and the respondent would not be entitled to claim any
damages for the non-supply of the list. He also
referred to the decision in Jagad Bandhu Chatterjee v. Smt. Nilima Rani & Ors., (1969) 3 SCC 445 wherein at para 5, it is stated “it is open to a
promisee to dispense with or remit, wholly or in part, the performance of the
promise made to him or he can accept instead of it any satisfaction which he thinks
fit.” He also relied upon the judgment in Babulal Badriprasad Varma v. Surat Municipal Corporation & Ors., (2008) 12 SCC 401 and pointed out that in that case, the Court has
considered various judgments on the issue of waiver in paragraph 42 to 49,
which laid down that waiver amounts to abandonment of right in such a way that
the other parties entitled to plead the abandonment by way of confession and
avoidance if the right is thereafter asserted and is either expressed or
implied from the conduct. Number of other judgments laying down the same
proposition of law were also referred to.
34) Additionally, it was submitted that the appellant had on
June 17, 1998 permitted the respondent to make feeder-wise installation
irrespective of B-I,
B-II and B-III locations.
Between June 17, 1998 to December 21, 1998 i.e. for a period of more than six
months, the respondents had all the B-II locations available to them which is
12,555 out of which they only installed 2014
and they did not install 10541 B-II locations which were the locations where
the respondent had themselves installed the contract objects against tender of
1993 and 1994 and were maintaining the said objects at the time when the
present tender was awarded and hence were in the complete knowledge of the said
locations. The endeavour was to show that the respondent was aware of
sufficient number of locations, even B-II locations and, therefore, there was
no reason to terminate the contract and, in fact, it is the respondent which
had failed to perform its obligations under the contract and was, thus,
responsible for the breach thereof. On that premise, the submission was that
award of the Arbitral Tribunal qua the uninstalled
object is patently illegal and it also shocks the conscience of the Court and
is liable to be set aside as being opposed to public policy. Specifically adverting
to the damages awarded qua
installed objects, it was argued
that the work order clearly provided that each contract object was a separate
contract between the appellant and the respondent and, therefore, it was
incumbent upon the Arbitral Tribunal to decide as to what fault had been
committed by the appellant qua
the installed objects before
granting any damages for the same. Absence of this exercise, contended the
learned senior counsel, had rendered the award illegal and in violation of public
policy as mentioned in Section 34 of the Act.
35) While questioning the damages awarded in respect of objects
not even manufactured; quantum of damages awarded by the Tribunal and failure
on the part of the respondent to mitigate the losses, the same arguments were
advanced which were taken before the High Court as well. It is also submitted
that the High Court committed serious error in rejecting the chamber summons.
ARGUMENTS IN REPLY BY THE RESPONDENT :
36) Mr. Dada, learned senior counsel appearing for the respondent,
strongly refuted all the aforesaid submissions of the appellant and made
earnest effort to show that the entire approach of the Arbitral Tribunal in
dealing with the issues and awarding the damages was correct in law and this
award was rightly held by the learned Single Judge as well as the Division Bench
of the High Court.
37) At the outset, Mr. Dada emphasized the crucial nature of
the contract in question, which was essentially for operating lease for ten
years in respect of energy saving devices which were to be installed by
respondent No.2 on the locations to be given by the appellant herein. He
pointed out that since it was a contract for operating these devices on lease
basis, entire investment was to be made by respondent No.2 and the appellant
was only to give the lease rent, that too on the condition that contract
objects were working satisfactorily. Further, the contract being a ‘lease’ contract,
the ownership of the equipment had to remain with respondent No.2 and was never
to be transferred to the appellant. In the aforesaid scenario, argued the
learned senior counsel for respondent No.2, respondent No.2 could perform its part
of the contract of installation of objects only on furnishing the DTC
locations. He argued that the appellant failed to discharge this obligation
and, thus, committed fundamental breach of the contract. This has been held so
by the Arbitral Tribunal and this very finding was upheld by the High Court as
well. Submission was that this being a finding of fact, the breach of contract
on the part of the appellant stands established.
38) Elaborating on this aspect, it was contended that the appellant
made an unequivocal representation to respondent No.2 on 14.07.1997 that complete
lists for DTC locations, including Schedule B-II, are ready with the district
offices. Respondent
No.2 acted upon the said representation and commenced installation in November
1997. On 20.04.1998, the appellant threatened respondent No.2 with liquidated
damages and warned that time will not be extended for installation. This letter
glossed over the fact that DTC locations were withheld by the district offices
of the appellant. Both parties were ad idem that time
had started to run and installation was to be completed before 18.03.1999
(twenty months from 18.07.1997, i.e. the date of receipt of the letter dated
14.07.1997 from the appellant). Despite
rigorous follow up and distress appeals by respondent No.2 through more than
120 letters, the appellant did not furnish complete lists of DTC locations. On
21.12.1998, the appellant directed the work to proceed strictly in the sequence
– Kolhapur, Nasik and Aurangabad Zones, with further sequences B-1, B-2 and
B-3. The appellant stopped work under B03 indefinitely without assigning any
reason. However, even till 19.02.1999, respondent No.2 was not provided with
complete list of B-I locations in Kolhapur. Despite representation of
11.02.1999 from Technical Member of the appellant to give lists within four
days, i.e. by 15.02.1999, no lists were received. Realizing the futility of expecting
cooperation from the appellant, respondent No.2 terminated the contract on
19.02.1999.
39) It was further
submitted that respondent No.2 still ‘offered’ to maintain the 17294 installed
objects (however, the appellant was admitting installation of only 7000
contract objects as of July 199, as stated by respondent No.2 in the interim
application filed before the Arbitrators), provided that payment was made
without demur or dispute – obviously alluding to the financial blockade by NIL performance
certificates and fabrication of failure reports. Respondent
No.2 gave the appellant seven days to convey if the said “offer” was
acceptable. Admittedly, the appellant did not accept the offer and proceeded to
make a counter claim against respondent No.2 on the footing that respondent
No.2 had abandoned the entire contract on 19.02.1999, including that for installed
objects.
40) It was next argued by Mr. Dada that after the disputes
were referred to the Arbitral Tribunal, it went into the length and breadth of
each issue in minute detail. This Tribunal consisted of eminent retired Judges
who scanned through the deposition of witnesses produced before it as well as
other documentary evidence. 125 sittings, over a period of five years, were
held in the process, which culminated into a fully reasoned and unanimous award
dated 18.06.2004 running into 150 pages, as per which the matter was decided in
favour of respondent No.2 and against the appellant. His argument was that most
of the submissions of the appellant were questioning the findings of facts only
and this Court would not embark on such a journey and decide correctness
thereof in exercise of its jurisdiction under Article 136 of the Constitution.
41) We find adequate force in the aforesaid submission of Mr. Dada.
Let us first take note of these findings:
FINDINGS OF FACTS :
42) Reasoning
contained in the Award reveals following salient findings returned by the
Arbitral Tribunal:
(i) The appellant prevented respondent No.2 from performing the
contract.
(ii) Respondent No.2
was ready and willing to perform the contract all throughout.
(iii) The appellant
chose not to examine any of its Superintending Engineers who were in-charge for
giving DTC locations to respondent No.2 and, as found by the Arbitral Tribunal,
they were the kingpins of each circle for performance of the contract.
(iv) There is
considerable merit in the submission of respondent No.2 that the Minutes of the
Meeting dated 24.06.1998 is a fabricated document.
(v) It is not
possible to accede to the submission of the appellant that respondent No.2 had
adequate lists of locations available and still failed to install the contract objects.
(vi) It is obvious
that there is something seriously wrong in the working of the appellant. Once a
letter is listed in the affidavit of documents, it is surprising how the letter
was not traceable. Be that as it may, the fact remains that prior to the date
of termination of contract, at least in three Circles, the appellant had
directed stoppage of installation work.
(vii) It is
unfortunate that the Head Office of the appellant lacked control over the field
offices and which ultimately led to the failure of the project. It is futile to
even suggest that the breach was not a fundamental one.
(viii) Respondent No.2
was ready and willing to perform their part of the contract while the appellant
committed a breach by failure to supply DTC locations as per the terms of the contract.
(ix) Respondent No.2
invested Rs.163 crores in the project.
(x) The appellant
failed to prove that deductions effected in the Performance Certificates were
proper.
(xi) The appellant
indulged in tampering the commissioning reports produced on record. The attempt
does not behove to a statutory body and requires to be deprecated. The attempt
made by the appellant by producing documents which are tampered with and which
are not genuine indicates that the appellant was willing to go to any extent to
make allegations against respondent No.2.
(xii) The appellant
did not make available large number of documents disclosed in the affidavit of
documents on the ground that the same are not available.
(xiii) Counter claim
of the appellant is misconceived and is nothing short of counter blast to the
claim made against respondent No.2.
(xiv) It was the
appellant and appellant alone who had committed fundamental breaches of the
terms of the work order.
(xv) The appellant
has raised untenable and unsustainable defences which led to considerable delay
in concluding the proceedings.
These
are findings of facts based upon the material evidence that emerged on the
record of the case.
TERMINATION OF CONTRACT WAS VALID AND JUSTIFIED :
43) Categorical findings are arrived at by the Arbitral
Tribunal to the effect that insofar as respondent No.2 is concerned, it was always
ready and willing to perform its contractual obligations, but was prevented by
the appellant from such performance. Another specific finding which is returned
by the Arbitral Tribunal is that the appellant had not given the list of
locations and, therefore, its submission that respondent No.2 had adequate
lists of locations available but still failed to install the contract objects
was not acceptable. In fact, on this count, the Arbitral Tribunal has commented
upon the working of the appellant itself and expressed its dismay about lack of
control by the Head Office of the appellant over the field offices which led to
the failure of the contract. These are findings of facts which are arrived at
by the Arbitral Tribunal after appreciating the evidence and documents on
record. From these findings it stands established that there is a fundamental
breach on the part of the appellant in carrying out its obligations, with no
fault of respondent No.2 which had invested whooping amount of Rs.163 crores in
the project. A perusal of the award reveals that the Tribunal investigated the conduct
of entire transaction between the parties pertaining to the work order,
including withholding of DTC locations, allegations and counter allegations by
the parties concerning installed objects. The arbitrators did not focus on a
particular breach qua
particular number of objects/class
of objects. Respondent No.2 is right in its submission that the fundamental
breach, by its very nature, pervades the entire contract and once acted
committed, the contract as a whole stands abrogated. It is on the aforesaid basis
that the Arbitral Tribunal has come to the conclusion that the termination of
contract by respondent No.2 was in order and valid. The proposition of law that
the Arbitral Tribunal is the master of evidence and the findings of fact which
are arrived at by the arbitrators on the basis of evidence on record are not to
be scrutinised as if the Court was sitting in appeal now stands settled by
catena of judgments pronounced by this Court without any exception thereto. [(See – Associate Builders v. Delhi Development Authority, (2015) 3 SCC 49, and S. Munishamappa v. B. Venkatarayappa & Ors., (1981) 3 SCC 260) 45)
44) At this stage, we may deal with the contention of the appellant
to the effect that the arbitrators have themselves recorded a finding that the
LC was still in operation and had not expired and, therefore, the finding of
the Tribunal that the contract was terminated validly was self contradictory. Though
this contention appears to be attractive in the first blush, we find no
substance in the same on deeper examination thereof. It was rightly contended
by Mr. Dada that the Arbitral Tribunal has held that since the contract was
terminated on 19.02.1999, the appellant was not required to renew the LC. In other
words, since there was no contract in existence after 19.02.1999, there could
not be a breach. It is APT to quote the following discussion from the award of
the arbitrators:
“24...The grievance
of the Claimants that by not renewing letter of credit which expired on April
30, 1999, the Respondents have committed the breach, cannot be accepted. In the
first instance, the Claimants cannot complain about non-renewal of Letter of
Credit on April 30, 1999 when the claimants themselves have terminated the
contract by notice dated February 19, 1999. Secondly, the claimants have
invoked the arbitration on April 13, 1999 and these events having taken place
prior to April 30, 1999, there was no point in Respondents renewing Letter of
Credit for the benefit of the Claimants.”
46) By
the aforesaid analysis, the Arbitral Tribunal did not accept the contention of
respondent No.2, which was predicated on non-renewal of the LC. However, the
context in which these observations are made is abundantly clear. The Arbitral
Tribunal had confined the discussion revolving around the contention of respondent
No.2 as to why the LC was not extended even after 30.04.1999. In this hue, it
was observed that there was no reason or rationale in doing so when the
contract had itself come to an end as it had been terminated by respondent No.2
itself vide notice dated 19.02.1999. It would not follow therefrom that respondent
No.2 was wrong in terminating the contract. Insofar as the termination of the
contract is concerned, the Arbitral Tribunal dealt with the issue specifically
and on independent examination thereof had came to the conclusion that
respondent No.2 was justified in the said action as there were other breaches on
the part of the appellant. It is to be borne in mind that non-renewal of LC was
not the only breach alleged by respondent No.2, which had asserted various
other acts of breach on the part of the appellant. In this behalf, Mr. Dada
drew our attention, and rightly so, to the letter dated 18.11.1998 which is contemporaneous
to the letter of termination, wherein respondent No.2 categorically alleged
fabrication of Commissioning Reports of installed objects and the financial
blockade created by the issue of NIL Performance
Certificates by the appellant. This letter is referred to in the letter of
19.02.1999 by incorporating references contained in the letter dated
23.12.1998. Respondent No.2, in its Statement of Claim, has also asserted the
harassment and deliberate breach of the appellant in the course of installation
of objects such as fabrication of failure reports and commissioning reports,
obstructing payments by bogus deductions in performance certificates and other
wrong practices of the appellant staff. The serious grievances of respondent
No.2 in respect of installed objects were considered at length by the Arbitral
Tribunal and accepted the same.
47) We have already referred to these findings hereinabove. Learned
senior counsel appearing for respondent No.2 referred to the judgment of this
Court in Juggilal Kamlapat v.
Pratapmal Rameshwar, (1978) 1 SCC 69 wherein it has been held that repudiation of a contract
can be justified on the basis of any ground that existed in fact, even though
not stated in the correspondence. Following passage from the said judgment
needs a quote:
“23. It was also contended
that the defendant not having raised the plea in their correspondence with the
plaintiff that the delivery orders tendered were defective, was estopped from
justifying their requisition of the contracts on that around. As the High Court
has pointed out no case of estoppel was pleaded by the plaintiff and, therefore,
it was the plaintiff who should be precluded from raising the question of
estoppel. Apart from that, the law permits defendant to justify the repudiation
on any ground which existed at the time of the repudiation whether or not the
ground was stated in the correspondence. (See
Nune Sivayya v. Maddu
Ranganayakulu, AIR 1935 PC 67 :
62 IA 89, 98).”
48) One more aspect
needs to be adverted to at this stage which
incidentally arises in view of the submission of Mr. Vikas Singh, learned
senior counsel appearing for the appellant.
49) It was argued that respondent No.2 should have installed
objects at least under category B-2, even if there was breach on the part of
the appellant in supplying locations for categories B-1 and B-3. This was
refuted by learned senior counsel appearing for respondent No.2 on the round
that the Arbitral Tribunal had specifically considered and rejected this
argument and the approach of the arbitrators is even upheld by the learned
Single Judge as well as the Division Bench of the High Court. We may point out
that the Arbitral Tribunal has dealt with this aspect in the following manner:
“Datar was asked a specific question as to how the Claimants
did not install the contract objects in category B-II and the answer of the
witness was in four parts. The witness claimed that (a) the contract was
entered into considering the commercial efficacy of installing given quantity
of B-I and B-III categories to counter balance low revenue from B-II category.
The witness claimed that as the Respondents did not supply the list of
categories B-I and B-III, the Claimants were entitled to withhold installation
of category B-II; (b) The annually installed at Nasik under B-II category was
install at Nasik under B-II category was relatively less obstructive in Nasik
Circle; (c) the locations under category B-II were intervened with locations of
categories B-I and B-III and it was practically unviable to install objects of
category B-II selectively. The list of B-II category was also required to be re
identified by the Respondents separately as was done for the Nasik Circle and
(d) the Respondents unilaterally willingly revoked the permission granted
earlier to install simultaneously by letter dated December 21, 1998. Some of
the reasons given by the witness cannot be termed as unreasonable in the facts
and circumstances of the case. It cannot be overlooked that in respect of installation
of objects under category B-II, the Claimants were entitled only to the rates
fixed under year 1993 and 1994 contract till the expiration of six year period
while in respect of categories B-I and B-III, the lease rentals were
considerably high.
In
any event, it does not lie in the mouth of the Respondents to urge that the
claimants should have installed contract objects under category B-II when specific
directions were given on December 21, 1998 to install objects under category
B-II only after completion of installation under category B-I. The Respondents
claimed that 16,477 locations were available on February 19, 1999 but that is
not correct because taking into consideration 10,541 locations of category B-II
the available locations out of B-I and B-III categories were 5,932.”
50) The Division Bench dealt with this contention in the following
manner:
“In our view from the material on
record, it is abundantly clear that supply of DTC Lists was a fundamental term
of the Work Order and MSEB had miserably failed in complying with the said fundamental
term and there was a breach on the part of the MSEB in supplying the DTC
locations which eventually prevented DSL from installation of contract objects.
It has to be noted here that after the work order was issued by MSEB, DSL had
to make necessary arrangements for the purpose of carrying out the process of
installation of the contract objects.
This
included procurement of raw material from a foreign country, starting the
process of manufacturing gadgets, making arrangements for transportation of these
contract objects to the places where the said gadgets were to be installed,
employment of trained, skilled and other staff, making available vehicles for transporting
these contract objects to the DTC location where they were to be installed and,
finally, co-ordinating with the Officers of MSEB so that after the contract
objects were installed, a Certificate of installation could be given by the
Officers of MSEB so that from that point onwards, lease rentals could become
payable to DSL. It has to be borne in mind that the nature of the Work Order
was such that it was in the interest of DSL to ensure that the contract objects
are installed and certificates to that effect are obtained from the Officers of
MSEB. It does not sound to reason that after having invested huge amount of almost
Rs 163 crores, as observed by the Tribunal in the Award, DSL would not install
the objects because it was in their interest to get the objects installed so that
returns on their huge investment would start thereafter. It is inconceivable
therefore that though DTC Lists were available, DSL would not install the contract
objects. Various facts and figures were given by MSEB to show that DTC
locations were known to DSL and yet they had failed in installing the contract objects
is without any substance. It cannot be forgotten that, initially, the sequence
of installation was Kolhapur, Nasik and Aurangabad. This sequence was later on
changed to Nasik, Kolhapur and Aurangabad.
This
was again changed and permission was given to DSL to install the objects at any
time at any place and, lastly, again, this was changed and direction was given to
DSL to adhere to the sequence as per the Work Order. This being the position,
even assuming that B-II Lists were available, DSL could not have installed these
contract objects because they were asked to follow the schedule again by letter
dated 21/12/1998 and, therefore, even if the lists were available, it was not
possible for DSL to simultaneously install all those objects since they were
told to adhere to the sequence in the Work Order if the lists of locations
under B-I were not given, even assuming that they had B-II lists of locations
they could not have and were not actually allowed to install at the said B-II
locations. It has come on record that more than 10,000 objects were manufactured
and ready for installation. There is no earthly reason why DSL would fail to
install the objects which were inspected and ready for installation. The only
obvious reason would be that they were unable to do so on account of various
orders which were passed by MSEB from time to time preventing them from performing
their obligation. MSEB has not examined any of its Superintending Engineers who
were in charge of supplying the Lists. The cumulative effect of all the material
which has been brought on record is that it clearly demonstrates the failure on
the part of MSEB in supplying the Lists of DTC locations which was a
fundamental term of the contract.”
51) We agree with
the contention of respondent No.2 that these are pure findings of facts and
there is no perversity therein. It may, however, be pointed out that out of
12555 B-2 category objects under the work order, 9515 objects were to be
installed in Kolhapur Zone, i.e. 76% of the said category. Vide letter dated 14.07.1997,
the Chief Engineer, Kolhapur Zone admittedly directed respondent No.2 to first
complete new installation (B-1 and B-3) and only thereafter take up
installation under category B-2. The locations for B-1 and B-3 from Kolhapur
were admittedly never furnished. Therefore, this contention of the appellant
also warrants a rejection.
52) The award of the Arbitral Tribunal having been affirmed
by the learned Single Judge as well as the Division Bench of the High Court,
that too after dealing with each and every argument raised by the appellant in
detail, which is negatived, we hold that Mr. Dada is correct in his argument
that there is no question of law which is involved herein and the only attempt
of the appellant was to re-argue the matter afresh, which was impermissible.
AWARD OF DAMAGES :
53) Refuting the
argument of the appellant that there was no breach in respect of 17294
installed objects and, therefore, no damages were payable in that behalf, Mr.
Dada pointed out that the appellant had itself submitted before the Arbitral
Tribunal as under:
“The
respondents submitted that the claimants at the most would be entitled to the
costs of the objects installed, i.e. cost of 17294 contract objects. Alternatively
it was submitted that the claimants would be entitled to lease rent for
reasonable period after deducting the cost of maintenance and taking out of print
outs.”
He also pointed out that identical
submission is to be found in the written submissions filed by the appellant
before the Arbitral Tribunal at para 13. According to him, the arbitrators
accepted the said submission of the appellant and awarded damages. The appellant
is, therefore, not at all entitled to invoke public policy to challenge the
award on the said premise. This aspect has been considered by the Division
Bench at para 73, which has already been reproduced above.
54) We see substance in the contention of respondent No.2
and are of the opinion that the appellant cannot now turn around and raise
objection to the award of damages which are measured having regard to the loss
suffered by respondent No.2 in terms of lease rent for reasonable period for
which it would have been entitled to otherwise.
55) That apart, we also find that the Arbitral Tribunal,
while awarding the damages, has relied upon the judgment of this Court in Union of India &
Ors. v. Sugauli Sugar Works (P)
Ltd., (1976) 3 SCC 32 wherein a
cardinal principle of damages had been laid down to the effect that the injured
party should be placed in as good a position as money could do as if the
contract had been performed. Following passage from the said judgment was kept in
mind by the Arbitral Tribunal:
“22. The
market rate is a presumptive test because it is the general intention of the
law that, in giving damages, for breach of contract, the party complaining should,
so far as it can be done by money, be placed in the same position as he would
have been in if the contract had been performed. The rule as to market price is
intended to secure only an indemnity to the purchaser. The market value is
taken because it is presumed to be the true value of the goods to the purchaser.
One of the principles for award of damages is that as far as possible he who
has proved a breach of a bargain to supply what he has contracted to get is to
be placed as far as money can do it, in as good a situation as if the contract
had been performed. The fundamental basis thus is compensation for the pecuniary
loss which naturally flows from the breach.
Therefore,
the principle is that as far as possible the injured party should be placed in
as good a situation as if the contract had been performed. In other words, it
is to provide compensation for pecuniary loss which naturally flows from the
breach. The High Court correctly applied these principles and
adopted the contract price in the facts and circumstances of the case as the
correct basis for compensation.”
56) In the instant
case, applying the aforesaid principle, the Arbitral Tribunal, for the purpose
of classification, considered a 30% reduction in lease rent to compute damages
for installed objects, 50% reduction in lease rent to compute damages for manufactured
but uninstalled objects and the bare cost of raw materials for the objects not
manufactured. No pendente
lite interest was awarded, though
the proceedings went on for five and a half years. Thus, the Arbitral Tribunal
awarded almost the same amount as was invested by respondent No.2 for the
project. Interest
was awarded only @ 10% per annum from the date of the award as opposed to the
prevailing bank rate of about 21%. The
aforesaid being a reasonable and plausible measure adopted by the Arbitral
Tribunal for awarding the damages, there is no question of interdicting with
the same.
57) It may be noted that Mr. Dada had argued that it was incumbent
upon the Arbitral Tribunal to take into account the practices of leasing trade
when making the award, having regard to the provisions of Section 28(3) of the
Indian Contract Act, 1872. He had drawn our attention to Article 13(2) of
UNIDROIT Convention on international lease, which stipulates as under:
“Where the lessee’s default is substantial, then subject
to paragraph 5 the lessor may also require accelerated payment of the value of
the future rentals, where the leasing agreement so provides, or may terminate
the leasing agreement and after such termination: (a) recover
possession of the equipment; and (b) recover such
damages as will place the lessor in the position in which it would have been had
the lessee performed the leasing agreement in accordance with its terms.”
58) In the aforesaid backdrop, we agree with the approach of
the High Court in spelling out the proposition of law that once it is established
that the party was justified in terminating the contract on account of
fundamental breach thereof, then the said innocent party is entitled to claim
damages for the entire contract, i.e. for the part which is performed and also
for the part of the contract which it was prevented from performing. We may
usefully refer to the following dicta laid down in Suisse Atlantique
Societe d'Armament SA v. NV Rotterdamsche Kolen
Centrale, 1966 A.C. 361 (pages 397-398):
“...if facts of that kind could be proved I think it
would be open to the arbitrators to find that the respondents had committed a
fundamental or repudiatory breach.
One
way of looking at the matter would be to ask whether the party in breach has by
his breach produced a situation fundamentally different from anything which the
parties could as reasonable men have contemplated when the contract was made.
Then
one would have to ask not only what had already happened but also what was likely to happen in future.
And
there the fact that the breach was deliberate might be of great importance.
If
fundamental breach is established the next question is what effect, if any,
that has on the applicability of other terms of the contract. This question has
often arisen with regard to clauses excluding liability, in whole or in part,
of the party in breach. I do not think that there is generally much difficulty
where the innocent party has elected to treat the breach as a repudiation,
bring the contract to an end and sue for damages. Then the whole contract has
ceased to exist, including the exclusion clause, and I do not see how that
clause can then be used to exclude an action for loss which will be suffered by
the innocent party after it has ceased to exist, such as loss of the profit which
would have accrued if the contract had run its full term...” (emphasis
supplied)
59) We, thus, do not find any infirmity in the manner in
which damages are awarded in favour of respondent No.2.
RE : MITIGATION OF DAMAGES
60) Mr.
Rafique Dada also countered the argument of the appellant on mitigation of
damages with the submission that this aspect was specifically considered and
the contention of the appellant in this behalf was rejected not only by the
Arbitral Tribunal but by the High Court as well. He referred to the relevant portion
of the discussion in the award as well as the judgments. We
find that the Arbitral Tribunal has dealt with this aspect and held that the
contract objects were custom built in the following manner:
“55. Respondents submitted that the Claimants did not
make any efforts to mitigate the loss suffered. The submission is without any
merit for more than one reason. In the first instance, the contract objects manufactured
in pursuance of the orders of the Respondents were custom built i.e. to the specifications
laid down by the Respondents and these contract objects cannot be disposed in
open market. Datar deposed with reference to Exh. C 16 that efforts were made
to sell the contract objects stranded in the factory to other Electricity
Boards but those efforts did not succeed. It was contended by the Respondents
that the claimants should have dismantled the stranded contract objects and
sold the components thereof. The submission is only required to be slated to be
rejected. Once an electronic instrument is dismantled, then the value almost becomes
nil. In any event, the Claimants have established that efforts were made to
mitigate the loss.”
61) The learned
Single Judge as well as the Division Bench of the High Court has given its
imprimatur to the aforesaid findings. It,
therefore, becomes apparent that the objects in question were manufactured by
respondent No.2 to suit the specific needs of the appellant ad they could not
be used otherwise. Therefore, there was no possibility on the part of
respondent No.2 to make an endeavour to dispose of the same in order to
mitigate the loses.
RE : WAIVER
62) The argument of
the appellant on waiver is also successfully met by respondent No.2. Submission
of Mr. Dada, on this argument, was that both parties went to trial before the Arbitral
Tribunal on the basis that the time to start work under the contract had
commenced with reference to letter dated 14.07.1997 of the appellant signed by
the Chief Engineer who was the competent authority under the contract. The same
Chief Engineer insisted, by letter dated 20.04.1998, that liquidated damages
would be imposed if the work was not completed in time. We may point out that
the Arbitral Tribunal considered and rejected this argument of waiver, as set
up by the appellant, in the following words:
“18... It was then contended that the Claimants had waived the
right to receive the lists of locations from the Respondents. By reference to
clause 5.1 of the work order, it was submitted that the Claimants were to
commence installation within four months from (a) the date of the work order;
(b) opening of Letter of Credit and (c) on receipt of complete list of
locations, whichever is later. It was contended that the Claimants were
entitled to wait till all the lists were supplied to installation, but as the
Claimants commenced installation even though the entire lists were not
supplied, it should be concluded that the Claimants have waived their right.
The submission is desperate and wholly unfair. The Respondents were in a hurry
to complete the installation within a period of 20 months with an object to
save the large amount lost due to loss of energy. Merely because the Claimants acted
in a reasonable manner and did not insist upon the terms of the contract, it is
absurd to suggest that the Claimants waived their right to complain about non-supply
of lists of locations. It was then submitted that the Claimants had installed
contract objects on the oral instructions and on the basis of chits issued by
some of the Officers of the Respondents and that was contrary to the terms of
the work order which provided that installation should be only on locations, the
lists of which are given in accordance with the format at Annexure ‘E’ to the
work order. It was also submitted that on 155 locations at Jalgaon, Dhule and Aurangabad,
the lists were received by the Claimants from Authorities who were not
competent to issue such lists. The submission has no merit because while
undertaking such a huge project, the parties were not keen on strict compliance
of each and every term and condition of the contract. Such an instance would
have defeated the contract at once because the contract had to be carried out
over a large area and with the interaction of large number of people. These factors
cannot establish that the claimants have waived their right to complaint about
the failure to supply lists of location...”
63) Mr.
Vikas Singh, learned senior counsel appearing for the appellant, referred to
and relied upon various judgments in support of his contention. These judgments
deal with the scope of interference in the awards passed by the arbitrators. It
is not even necessary to deal with these judgments inasmuch as, on the facts of
this case, as discussed in detail hereinabove, none of the judgments gets
attracted. Likewise, effort on the part of the appellant to rely upon the
judgment of the learned single Judge of the High Court in the first round is
futile as that was set aside by the Division Bench and matter was remitted back
to the single Judge of the High Court to decide it afresh.
RE: ORDER ON CHAMBER SUMMONS
64) Three chamber summons were taken out by the appellant during
the pendency of this appeal before the Division Bench. By these chamber
summons, the appellant intended to amend the petition which was filed by it
under Section 34 of the Act as well as the appeal. The High Court after
detailed discussion in the impugned judgment rejected these summons. We find
that the amendment sought was highly belated. Arbitration petition filed under
Section 34 of the Act was sought to be amended after a delay of eight years.
Further, the amendment in the appeal, taking those very grounds on which
amendment in the arbitration petition was sought, was sought after a delay of
3½ years. The High Court, thus, rightly rejected these summons and it is not necessary
to have any elaborate discussion on these aspects.
65) In the ultimate analysis, having found no merit in any
of the arguments raised by the appellant, the appeal is dismissed with costs.
Comments
Post a Comment