Court shall not Intervene with the Subject Matter of Arbitration unless Injustice is caused to either of the Parties [SC Judgment]
Arbitration and Conciliation Act, 1996 - Ss. 5 & 34 - Court shall not intervene with the subject matter of arbitration unless injustice is caused to either of the parties.
Held:- The primary object of the arbitration is to reach a final disposition in a speedy, effective, inexpensive and expeditious manner. In order to regulate the law regarding arbitration, legislature came up with legislation which is known as Arbitration and Conciliation Act, 1996. In order to make arbitration process more effective, legislature restricted the role of courts in case where matter is subject to the arbitration. Section 5 of the Act specifically restricted the interference of the courts to some extent. In other words, it is only in exceptional circumstances, as provided by this Act, the court is entitled to intervene in the dispute which is subject matter of arbitration. Such intervention may be before, at or after the arbitration proceeding, as the case may be. [Para 8]
Contract Law - Parties are free to decide their own terms and conditions in case of a contract - If any departure would be allowed from the terms and conditions of the contract, then it would destroy the basic purpose of the contract provided such conditions shall not be arbitrary.
In the instant case, Clause 19 of the special conditions deal with issue of bar on reimbursement of certain payments on account of escalation. On a plain reading of abovementioned clause, prima facie, it appears that the appellant made it clear that the contractor shall quote their rate after having regard to this clause that no reimbursement regarding any escalation whatsoever be made to the contractor if any such escalation takes place during the subsistence of the contract which the respondent with open eyes had agreed. The word “whatsoever” as used in Clause 19 suggests that even any escalation takes place due to the action of the government would also not be reimbursed. On a plain reading of Clause 6.3 read with Clause 19, it is evident that it was particularly made clear that no escalation would be reimbursed even in the case of Regulation. Hence, in the presence of such clauses, which respondent voluntarily agreed before accepting the contract, any departure cannot be allowed. In other words, now the respondent cannot claim reimbursement of excess of minimum wages on account of hike due to the Notification of the Government of Haryana. [Para 9 & 10]
Whether the Award of the arbitrator and the findings of the High Court are contrary to the express provision of Clause 19, according to which no escalation is permissible to the contractor for, inter alia, increase in wages of labour due to statutory hike, which the contractor may have to incur during the execution of the work on any account?
It is a settled law that the process of interpretation is based on the objective view of a reasonable person, given the context in which the contracting parties made their agreement. On a perusal of the said two paragraphs of the impugned judgment, we fail to understand that on what parameters the High Court has interpreted Clause 19 in light of Clause 25 of the Contract. Both the clauses stand on different footing. Clause 19 deals, inter alia, with the matter of wages whereas Clause 25 deals with the matter of Octroi Sales Tax and other Duties. Such interpretation adopted by the High Court is against the cardinal principle of law which says that the terms of the contract shall be construed by the courts after having regard to the intention of the parties. Courts ought not to take any hypothetical view as it may cause prejudice to either of the parties. It is pertinent to note here that Clause 19 does not start with any word “Subject to”. Moreover, there is no other provision in the contract which specifically allow the reimbursement of wages in case of escalation. In the absence of these things, we are of the considered view that it is not permissible in law that Clause 19 ought to be interpreted in light of Clause 25. Also in the impugned judgment, the High Court without having regard to the title and first part of Clause 25, interpreted Clause 19, along with the second part of Clause 25, which is against the cannons of law. To sum up, Clause 19 cannot be read in the light of second Part of Clause 25 as both stands on different footing i.e., deal with separate issues. Hence, the respondent-Contractor in the present case is not entitled to claim any escalation in minimum wages as it would be against the condition of Clause 19 read with Clause 6.3. In view of the above detailed discussion, we are of the considered view that the High Court erred in law. Accordingly, we are inclined to allow these appeals and set aside the decision of the courts below as also the Award. Parties to bear their own cost. [Paras 12 to 15]
CIVIL APPELLATE JURISDICTION
(R.K. AGRAWAL) AND (ASHOK BHUSHAN) JJ.
APRIL 19, 2018
CIVIL APPEAL NOS.
3994-3995 of 2018
(Arising out of Special Leave Petition Nos. 9743-9744 OF 2013)
Union of India ….Appellant(s)
Versus
M/s.
Varindera Constructions Ltd. Etc. …. Respondent(s)
Petitioner's Advocate : Shreekant N. Terdal
Respondent's Advocate : Umesh Kumar Khaitan
J U D G M E N T
R.K. Agrawal, J.
1) Leave
granted.
2) These
two appeals are preferred against the impugned common judgment and order dated
28.05.2012 passed by the High Court of Delhi at New Delhi in FAO (OS) Nos. 238 and
239 of 2012 whereby the Division Bench of the High Court dismissed the appeals
filed by the appellant herein while upholding the decision of learned single
Judge of the High Court. Since the moot question is same in these two appeals,
both would be disposed off by this common judgment.
3) Brief facts:-
(a)
The appellant herein is the Union of India and the respondent herein is the
Contractor. On 30.10.2006, the appellant floated two tenders for the
construction of the residential accommodations at Hissar. Pursuant to that, the
appellant received tenders of various companies.
(b)
Being the lowest quotation of the respondent- Contractor, its tender was
accepted by the appellant. The lump sum amount of these two contracts were Rs. 39,09,80,362.61
and Rs. 35,21,99,854.30 respectively. Consequently,
the appellant and the respondent-Contractor entered into formal contract and
laid down terms and conditions of the contract by which it was decided that
both would be bound and also added the clause of arbitration in case of
dispute.
(c) As per the terms of the contract, respondent started the work of
construction as per the schedule on 20.03.2007 and finally completed the work
within the stipulated extended time period of completion. At this juncture,
respondent submitted the final bill along with some additional claims. The
claim of additional amount was rejected by the appellant. As
a result, the respondent invoked the arbitration clause and the dispute was
referred to learned Arbitrator Shri Sunil Chopra, Chief Engineer (Contract) as
provided under the Contract.
(d)
Learned Arbitrator made the Award dated 24.08.2011. It
is pertinent to note here that the respondent referred total 12 claims in the
arbitration proceeding. Out of these claims, two were rejected by learned
Arbitrator and one claim is partly withdrawn by the respondent and the
remaining claims were decided in favour of the respondent.
(e)
Feeling aggrieved, the appellant filed OMP Nos. 890 and 891 of 2011 before the
High Court of Delhi. Learned single Judge of the High Court, vide common order
dated 16.03.2012, dismissed both the petitions and upheld the Award passed by
learned Arbitrator.
(f)
Being aggrieved with the said order, the appellant preferred two separate first
appeals being FAP (OS) Nos. 238 and 239 of 2012 respectively. However, the same
two appeals also got dismissed by the Division Bench of the High Court in limini vide judgment and order dated 28.05.2012.
(g)
As a result, the appellant has filed these two appeals by way of special leave
before this Court.
4) We
have given our thoughtful consideration to the submissions of learned senior
counsel for the parties and perused the material on record placed before us.
Point(s)
for consideration:-
5) The
present case is confined only to the extent as to whether the Award of the
arbitrator and the findings of the High Court are contrary to the express
provision of Clause 19, according to which no escalation is permissible to the contractor
for, inter alia, increase in wages of labour due to statutory
hike, which the contractor may have to incur during the execution of the work
on any account?
Rival
contentions:-
6) At the
outset, learned senior counsel for the appellant-Union of India contended that
the relationship of the appellant and respondent is governed by the terms and conditions
of the contract and as per Clause 19 of the special conditions, it is clearly
mentioned that “No
escalation, reimbursement whatsoever shall be made to the contractor for increase
in, inter-alia, wages of the labor during the execution of the contract”. Hence, the Notification issued by the
State of Haryana which increased the minimum wages of the labour during the
subsistence of the contract does not vest any right to the contractor to claim
any extra amount on account of labour wages. Hence, the impugned decision of
the High Court is liable to be set aside.
7) Per contra,
learned counsel for the respondent submitted that this Court need not interfere
with the order passed by the High Court and the arbitral Award under the question
as the challenge in the instant appeal does not fall within the contours of
Section 34 of the Arbitration and Conciliation Act, 1996 (for brevity “the Act”).
The alleged challenges pertain to certain claims relating to interpretation of
the contract which falls within the jurisdiction of the Arbitrator and findings
of facts which are final and binding between the parties, hence, this Court
ought not to interfere if the interpretation taken is plausible one and does
not shocks the conscience of this Court. Further, it was submitted that the
impugned decision of learned single Judge as well as the Division Bench of the
High Court is well-reasoned and based on the cannon of laws which does not call
for interference by this Court. Therefore, these appeals being devoid of merits
and deserve to be dismissed.
Discussion:-
8) The primary object of the arbitration
is to reach a final disposition in a speedy, effective, inexpensive and
expeditious manner. In order to regulate the law regarding arbitration, legislature
came up with legislation which is known as Arbitration and Conciliation Act,
1996. In order to make arbitration process more effective, legislature
restricted the role of courts in case where matter is subject to the arbitration.
Section 5 of the Act specifically restricted the interference of the courts to
some extent. In other words, it is only in exceptional circumstances, as
provided by this Act, the court is entitled to intervene in the dispute which
is subject matter of arbitration. Such intervention may be before, at or after
the arbitration proceeding, as the case may be. In short, court shall not
intervene with the subject matter of arbitration unless injustice is caused to
either of the parties.
9) It
is well-settled cannon of law that parties are free to decide their own terms
and conditions in case of a contract. In
the instant case, Clause 19 of the special conditions deal with issue of bar on
reimbursement of certain payments on account of escalation. It is apt to
re-produce the said clause 19 herein below:
“19. Reimbursement/Refund of
Variation in Prices:- No
escalation, reimbursement what so ever shall be made to the contractor for
increase in price of materials and fuels and wages of labour which the
contractor may have to incur during execution of the work on any account. The contractor
shall quote their rates accordingly.”
On
a plain reading of abovementioned clause, prima facie, it
appears that the appellant made it clear that the contractor shall quote their
rate after having regard to this clause that no reimbursement regarding any
escalation whatsoever be made to the contractor if any such escalation takes
place during the subsistence of the contract which the respondent with open
eyes had agreed. The word “whatsoever”
as used in Clause 19 suggests that even
any escalation takes place due to the action of the government would also not
be reimbursed.
10) At
this juncture, we would also like to mention that Clause 6.3 of special
conditions, particularly, deals with the present issue. For the sake of
convenience, it is reproduced herein below:
“Minimum Wages Payable:
6.1. Refer condition 51 of DG MAP general
conditions of contracts. The Contractor shall not pay wages lower than minimum
wages of labour as fixed by the Govt of India/State Govt/Union Territory
whichever is higher.
6.2
The fair wage referred to in condition 51 of DG MAP general conditions of
contracts will be deemed to be the same as the minimum wages payable as
referred to above.
6.3.
The contractor shall have no claim
whatsoever, if on account of local factor and /or regulations he is required to
pay the wages in excess of minimum wages as described above during the
execution of work.”
(Emphasis supplies by us)
On a plain reading of Clause 6.3 read
with Clause 19, it is evident that it was particularly made clear that no
escalation would be reimbursed even in the case of Regulation. Hence, in the
presence of such clauses, which respondent voluntarily agreed before accepting
the contract, any departure cannot be allowed. In other words, now the respondent
cannot claim reimbursement of excess of minimum wages on account of hike due to
the Notification of the Government of Haryana. If any departure would be allowed
from the terms and conditions of the contract, then it would destroy the basic
purpose of the contract provided such conditions shall not be arbitrary.
11) In
the impugned decision, the Division Bench of the High Court, at Para 6 & 7
held as under:
“6. Suffice
would it be to state that clause 19 and 25 have to be read harmoniously.
Whereas Clause 19 prohibits escalation to be paid with respect to the wages of
labour, Clause 25 requires minimum wage increase to be reimbursed to the
contractor upon there being an impact thereon by a law declared by the State
Government. The minimum wages, as we all know, are statutorily notified under
the Minimum Wages Act, 1948. We note that the learned arbitrator has granted
the benefits under the said head, but not fully recompensing the contractor the
37.46% increase in minimum wages. The reasoning given by the learned arbitrator
is that the contractor could have envisaged that there would be some increase
in wages during the period of contract.
7. The
interpretation by the learned arbitrator, if at all is faulty, is to the
detriment of the contractor, for the reason Clause 25, which commences with the
expression? However? is required to be read as an exception to Clause 19 and,
if so read, the entire increase in minimum wages which was result of a
government notification was required to be recompensed.”
12) It is a settled law that the process
of interpretation is based on the objective view of a reasonable person, given
the context in which the contracting parties made their agreement. On a perusal
of the said two paragraphs of the impugned judgment, we fail to understand that
on what parameters the High Court has interpreted Clause 19 in light of Clause
25 of the Contract. Both the clauses stand on different footing. Clause 19
deals, inter alia, with the matter of wages whereas Clause
25 deals with the matter of Octroi Sales Tax and other Duties. Such
interpretation adopted by the High Court is against the cardinal principle of
law which says that the terms of the contract shall be construed by the courts
after having regard to the intention of the parties. Courts
ought not to take any hypothetical view as it may cause prejudice to either of
the parties.
13) It
is pertinent to note here that Clause 19 does not start with any word “Subject to”. Moreover, there is no other provision in
the contract which specifically allow the reimbursement of wages in case of
escalation. In the absence of these things, we are of the considered view that
it is not permissible in law that Clause 19 ought to be interpreted in light of
Clause 25. Also in the impugned judgment, the High Court without having regard
to the title and first part of Clause 25, interpreted Clause 19, along with the
second part of Clause 25, which is against the cannons of law.
14) To
sum up, Clause 19 cannot be read in the light of second Part of Clause 25 as
both stands on different footing i.e., deal with separate issues. Hence, the respondent-Contractor
in the present case is not entitled to claim any escalation in minimum wages as
it would be against the condition of Clause 19 read with Clause 6.3.
15) In
view of the above detailed discussion, we are of the considered view that the
High Court erred in law. Accordingly,
we are inclined to allow these appeals and set aside the decision of the courts
below as also the Award. Parties
to bear their own cost.
Comments
Post a Comment