Having collected funds from Public for developing Roads, Government is not at liberty to back out [JUDGMENT]
Road
Development - Having taken a decision and having collected funds also for
developing the road, the State Government is not at liberty to back out from
the project, since the projects are still in force.
The State Government, and all other stake-holders interested in the development of Kochi city ought to have taken emergent steps in order to complete the project envisioned by the State Government as per Ext.P6 order. It is also clear that the Government have started to collect Rs.1/- additionally in the sale of Petrol and Diesel in order to pool the fund for the Projects envisioned under Ext.P6. Therefore, having collected the said fund, the State Government should have made every effort and endeavour to implement the project in a faster pace in order to ventilate the grievances of the residents of Kochi city, and other people visiting Kochi. It is quite disheartening to note from the report submitted by the District Collector, that the PWD had decided not to take up the project. However, having taken a decision as per Ext.P6 and having collected funds also for developing the road in question, the State Government is not at liberty to back out from the project, since the projects as per Ext.P6 are still in force.The project shall be completed by the State Government with the aid, assistance and co-operation of the stake-holders viz., the Kochi Corporation, the Greater Cochin Development Authority and the Kerala Road Fund Board, at the earliest possible time, and at any rate, within one year from the date of receipt of a copy of this judgment. The writ petition is disposed of accordingly.
Road Development - Charging additional sales tax at the rate of Rs.1/- per litre against the sale of petrol and diesel - When such activities are agreed to be undertaken by the State Government and many people have surrendered their rights over very valuable properties and the works accordingly are carried out partly, the Government attempting to resile from the activity is nothing but a clog on the fair public administration, thereby rendering the inaction to execute the promise arbitrary and illegal.
Road Development - Promise extended by the Government to the public - the failure on the part of the Government and other stake-holders to discharge the obligations, is nothing short of criminal breach of promise.
Facts of the Case
The Thammanam - Pulleppady road is one of the roads through which traffic congestion can be avoided in the city of Kochi. It is also evident that, many of the residents of the locality have co-operated with the implementation of the project by surrendering valuable lands in the prime location of Kochi city, free of cost. It is also evident from Ext.P6 order of the State Government specified above that the road is included in the Implementation of District Flagship Infrastructure Projects, and in order to accelerate the projects, the fund is met from the 50% share of Additional Sales Tax collected at the rate of Rs.1 per litre of Petrol/Diesel sold within the State, and this 50% share is expected to be Rs.200 Crores per annum. A total project cost of Rs.300 Crores is ordered to the road in question. However, in spite of all these developments taken place, nothing material has taken place to implement the project, other than widening the road wherever the public have surrendered the land free of cost.
The State Government, and all other stake-holders interested in the development of Kochi city ought to have taken emergent steps in order to complete the project envisioned by the State Government as per Ext.P6 order. It is also clear that the Government have started to collect Rs.1/- additionally in the sale of Petrol and Diesel in order to pool the fund for the Projects envisioned under Ext.P6. Therefore, having collected the said fund, the State Government should have made every effort and endeavour to implement the project in a faster pace in order to ventilate the grievances of the residents of Kochi city, and other people visiting Kochi. It is quite disheartening to note from the report submitted by the District Collector, that the PWD had decided not to take up the project. However, having taken a decision as per Ext.P6 and having collected funds also for developing the road in question, the State Government is not at liberty to back out from the project, since the projects as per Ext.P6 are still in force.The project shall be completed by the State Government with the aid, assistance and co-operation of the stake-holders viz., the Kochi Corporation, the Greater Cochin Development Authority and the Kerala Road Fund Board, at the earliest possible time, and at any rate, within one year from the date of receipt of a copy of this judgment. The writ petition is disposed of accordingly.
Road Development - Charging additional sales tax at the rate of Rs.1/- per litre against the sale of petrol and diesel - When such activities are agreed to be undertaken by the State Government and many people have surrendered their rights over very valuable properties and the works accordingly are carried out partly, the Government attempting to resile from the activity is nothing but a clog on the fair public administration, thereby rendering the inaction to execute the promise arbitrary and illegal.
Road Development - Promise extended by the Government to the public - the failure on the part of the Government and other stake-holders to discharge the obligations, is nothing short of criminal breach of promise.
Facts of the Case
The Thammanam - Pulleppady road is one of the roads through which traffic congestion can be avoided in the city of Kochi. It is also evident that, many of the residents of the locality have co-operated with the implementation of the project by surrendering valuable lands in the prime location of Kochi city, free of cost. It is also evident from Ext.P6 order of the State Government specified above that the road is included in the Implementation of District Flagship Infrastructure Projects, and in order to accelerate the projects, the fund is met from the 50% share of Additional Sales Tax collected at the rate of Rs.1 per litre of Petrol/Diesel sold within the State, and this 50% share is expected to be Rs.200 Crores per annum. A total project cost of Rs.300 Crores is ordered to the road in question. However, in spite of all these developments taken place, nothing material has taken place to implement the project, other than widening the road wherever the public have surrendered the land free of cost.
PRESENT THE HONOURABLE MR. JUSTICE
SHAJI P.CHALY
WEDNESDAY, THE 22ND DAY OF MAY 2019 /
1ST JYAISHTA, 1941
WP(C).No. 33103 of 2016
PETITIONER/S:
DR.
PRIYARENJINI S., CONSULTANT NEUROLOGIST, CC 55-1636B, VRINDAVANAM, KADAVANTHRA,
KOCHI-682 020.
BY
ADVS. DR.K.P.PRADEEP SMT.T.THASMI SRI.SANAND RAMAKRISHNAN
RESPONDENT/S:
1
THE STATE OF KERALA, REPRESENTED BY ITS SECRETARY (PUBLIC WORKS), GOVERNMENT
SECRETARIAT, THIRUVANANTHAUPRAM-695001.
2
DISTRICT COLLECTOR, ERNAKULAM, CIVIL STATION, KAKKANAD, ERNAKULAM-682030.
3
CORPORATION OF KOCHI, REPRESENTED BY ITS SECRETARY, CORPORATION OFFICE, PARK
AVENUE ROAD, ERNAKULAM-682011.
4
GREATER COCHIN DEVELOPMENT AUTHORITY, REPRESENTED BY ITS SECRETARY, GCDA
OFFICE, KADAVANTHRA, KOCHI, ERNAKULAM-682020.
5
KERALA ROAD FUND BOARD, TC 4/1654, MAYOORAM, BELHAVEN GARDENS, KOWDIAR P.O.,
THIRUVANANTHAPURAM-695003.
BY
ADVS. R1 & R2 - SMT. LATHA T. THANKAPPAN, SPECIAL GOVERNMENT PLEADER R3 -
SRI.S.CHANDRASENAN, SC, COCHIN CORPORATION R4 - SRI. ARUN ANTONY, SC
J U D G M E N T
Petitioner,
a resident of Kochi, has filed this writ petition seeking direction to the
respondents i.e., the State of Kerala, the District Collector, Ernakulam,
Corporation of Kochi, the Greater Cochin Development Authority and the Kerala
Road Fund Board, to complete the widening of Thammanam-Pulleppady road as per
the stipulations contained under Ext.P6 order of the State Government dated
10.06.2015 brought out for the implementation of District Flagship
Infrastructure Projects (DFIP) to accelerate Infrastructure Development in the
State of Kerala and according sanction thereto, and for other related reliefs.
Brief material facts for the disposal of the writ petition are as follows:
2. Kochi city is
one of the most congested cities within the State which requires proper and
sufficient attention from the public authorities for the improvement and
development of its infrastructures. Under the 2009 Jawaharlal Nehru National
Urban Renewal Mission (JNNURM) Scheme, the Central Urban Development Ministry
identified Kochi as one of the “One Million Populated Cities” in the country,
which requires special attention for infrastructure development. Kochi is also
selected as one among the 100 Indian cities for the “Smart City Mission Project”
piloted by the Central Government, during the year 2015.
3. Years back, the
local body viz., the Cochin Corporation as well as the State Government have identified
a project for widening of Thammanam- Pulleppady road into four lane traffic to
augment eastwest connectivity in the Kochi city, which is one among the key
solutions for de-congesting the existing Sahodaran Ayyappan Road, i.e., the
road leading from the South Junction to the Vyttila and Banerji road, i.e.,
Ernakulam North to Edappally. As per the Scheme formulated by the State
Government, the project requires a total cost of Rs.263 Crores for widening about
3.5 Kilometres of road with 22 metres of wide stretch and requires acquisition
of land having an extent of 4.0163 Hectares.
4. According to
the petitioner, an amount of Rs.25 Crores was allotted in the year 2011 for
land acquisition and another amount of Rs.25 Crores was allotted in the year
2015 for completing the land acquisition for the project. That being so, in the
year 2015, as per Ext.P6 order, the State Government have included the
Thammanam-Pulleppady Road widening under the District Flagship Infrastructures
Projects having an estimated cost of Rs.300 Crores and Administrative Sanction
was accordingly issued. The fund for meeting the project cost is being
collected by the State Government from the public through a newly introduced
Cess/Additional Sales Tax of Rs.1/- per litre collected from the sale of Petrol
and Diesel in the State.
5. The case
projected by the petitioner is that, even though sufficient funds are collected
from the public, the project is being protracted and the delay in implementing
the project is causing substantial injuries and hardships to the petitioner as
well as other inhabitants of the Kochi city. Therefore, the sum and substance
of the contention put forth by the petitioner is that, having collected fund
from the Infrastructure Development as per Ext.P6 and not expending the same
for the project envisioned, the action of the State Government, the local body
and other stake-holders are arbitrary and illegal, liable to be interfered with
by this Court, failing which, the difficulties and inconveniences faced by the
people visiting Kochi city will aggravate due to traffic congestion in the city.
6. A report is
filed by the District Collector, Ernakulam, i.e., the 2nd respondent,
dated 28.09.2017, in accordance with the directions issued by this Court, wherein
the details with respect to the widening required, the acquisition necessitated
and the fund for the project are put forth. Among other aspects, it is stated
that, the proposal for widening the road was included in the Budget Speech as Sl.No.34
and Stimulus Package-II as Sl.No.91 for an amount of Rs.10 Crores. It is also
pointed out that, the road length is 2.25 Kms., and the ownership of the road
is vested with the Kochi Corporation. That apart, it is stated that, part of
the aforesaid stretch is available for widening consequent to free surrender of
land made by the property owners on either side of the said existing road, and
altogether 94 persons have surrendered their land free of cost, and the extent
so surrendered is 1.1934 Hectares. It is further stated that, an extent of
4.0163 Hectares of land is yet to be acquired in order to complete the project,
and for that purpose, an amount of Rs.298 Crores is required. Therefore, the sum
and substance put forth by the 2nd respondent is that, unless and until the acquisition is
completed, the 22 metres width road envisaged cannot be completed.
7. It is also
pointed out that, as per the estimate prepared for land acquisition works in
four Villages within the limits of the Kochi Corporation an amount of Rs.136
Crores is required, i.e., excluding the amount already allotted and an
additional amount of Rs.111 Crores will be needed for the entire acquisition process.
It is further reported that the major portion of the structures coming under
the acquired land had been demolished by the Corporation. So much so, it is stated,
the Government have accorded Principal Sanction for Rs.3771.47 Crores for
improving major roads in each Districts as part of implementation of the
District Flagship Infrastructure Project for 21 roads, evident from Ext.P6.
Pulleppady-Thammanam road is included in that project and sanction is accorded
for Rs.300 Crores as per the Government Order dated 10.06.2015, and Administrative
Sanction for an amount of Rs.10 Crores has been obtained as per the Government
Order dated 01.11.2016 and the project is taken for implementation under “Infrastructure
Development Works-Special Investment Scheme” (Anti Recession Package) funded by
KIIFB.
8. It is further
pointed out that, in the meanwhile, the Kochi Corporation has decided to
entrust the remaining acquisition works with PWD Roads due to lack of fund and
the matter was brought to the notice of the Minister for PWD, in a meeting held
by the Public Works Department on 14.07.2017. However, no decision was taken.
But fact remains, in a meeting held in the presence of the Member of Parliament
of Ernakulam Parliamentary Constituency and MLA of the Assembly Constituency dated
22.07.2017, the Minister for PWD has stated that the PWD do not intent to undertake
the work of widening of the road in question.
9. I have heard
Dr. K.P. Pradeep, learned counsel for the petitioner and Smt. Latha T.
Thankappan, learned Special Government Pleader appearing for respondents 1 and
2, and perused the pleadings and the documents on record.
10. In my
considered view, the Thammanam- Pulleppady road is one of the roads through
which traffic congestion can be avoided in the city of Kochi. It is also
evident that, many of the residents of the locality have co-operated with the
implementation of the project by surrendering valuable lands in the prime location
of Kochi city, free of cost. It is also evident from Ext.P6 order of the State
Government specified above that the road is included in the Implementation of
District Flagship Infrastructure Projects, and in order to accelerate the
projects, the fund is met from the 50% share of Additional Sales Tax collected
at the rate of Rs.1 per litre of Petrol/Diesel sold within the State, and this
50% share is expected to be Rs.200 Crores per annum. A total project cost of
Rs.300 Crores is ordered to the road in question. However, in spite of all
these developments taken place, nothing material has taken place to implement
the project, other than widening the road wherever the public have surrendered
the land free of cost.
11. It is a common
feature and known to everybody that Kochi city is congested due to heavy
increase of traffic including heavy vehicles which are also passing through the
city limits in order to cater the needs of the Vallarpadam Project Container
Terminal etc. etc. So also, many of the godowns, major market and other Clearing
and Forwarding Agents are situated within Kochi Corporation, and therefore,
heavy vehicles are also to be taken in and out of the city limits. Even though
there are a few roads and bridges developed in order to divert the traffic from
the city to the National Highway and other roads, still there is huge traffic
congestion at peak hours of the day, and therefore, the only way out is
development of the roads from the city to the Highway and other broader roads situated
in and around Kochi city.
12. Furthermore,
due to the traffic congestion and emission from the vehicles, environmental
issues are also faced by the people apart from other issues like wasting fuel,
accidents and delay to meet up with emergent situations. The respondents shall
also bear in mind that the investments made for development of roads will
attain fruitful results in future. The State Government is also duty bound to
discharge the duties and obligations undertaken by it as per Ext.P6 order
published in the Gazette, treating it as a promise extended by the Government
to the public. So also, it has the characteristics of a firm offer made by the
Government to the public to carry out certain functions with the co-operation
of the public by charging additional sales tax at the rate of Rs.1/- per litre
against the sale of petrol and diesel. The public have thus accepted the said
offer by paying the additional tax, and therefore, the State Government is not
at liberty to withdraw from the offer. Moreover, when such activities are
agreed to be undertaken by the State Government and many people have
surrendered their rights over very valuable properties and the works accordingly
are carried out partly, the Government attempting to resile from the activity
is nothing but a clog on the fair public administration, thereby rendering the
inaction to execute the promise arbitrary and illegal. To put it otherwise, the
failure on the part of the Government and other stake-holders to discharge the
obligations, is nothing short of criminal breach of promise and undertakings
made by it in Ext.P6 order and interfering with the trust held by it for and on
behalf of the public.
13. Therefore, in
my considered view, the State Government, and all other stake-holders
interested in the development of Kochi city ought to have taken emergent steps
in order to complete the project envisioned by the State Government as per
Ext.P6 order. It is also clear that the Government have started to collect
Rs.1/- additionally in the sale of Petrol and Diesel in order to pool the fund
for the Projects envisioned under Ext.P6. Therefore, having collected the said
fund, the State Government should have made every effort and endeavour to
implement the project in a faster pace in order to ventilate the grievances of the
residents of Kochi city, and other people visiting Kochi. It is quite
disheartening to note from the report submitted by the District Collector, that
the PWD had decided not to take up the project. However, having taken a
decision as per Ext.P6 and having collected funds also for developing the road
in question, the State Government is not at liberty to back out from the
project, since the projects as per Ext.P6 are still in force.
14. Taking into
account all these aspects and bearing in mind the larger public interest, there
will be a direction to the State Government to convene a meeting of all the
stake-holders, within two months from the date of receipt of a copy of this
judgment, and finalize the schedule to complete the project and pump out
sufficient funds in order to implement the project in accordance with Ext.P6
and any additional funds required for completing the project. I make it clear
that, the project shall be completed by the State Government with the aid,
assistance and co-operation of the stake-holders viz., the Kochi Corporation,
the Greater Cochin Development Authority and the Kerala Road Fund Board, at the
earliest possible time, and at any rate, within one year from the date of
receipt of a copy of this judgment.
The
writ petition is disposed of accordingly.